New Year Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

SAP E_S4HCON2020 SAP Certified Technology Specialist - SAP S/4HANA Conversion and SAP System Upgrade Exam Practice Test

Demo: 7 questions
Total 53 questions

SAP Certified Technology Specialist - SAP S/4HANA Conversion and SAP System Upgrade Questions and Answers

Question 1

You are running an SAP ECC system. For which of the following activities does SUM allow you to use the Near Zero Downtime Maintenance (NZDM) capabilities?

There are 3 correct answers to this question.

Response:

Options:

A.

Apply SAP Support Packages.

B.

Upgrade the SAP system.

C.

Use DMO for SUM.

D.

Apply an Enhancement Package.

E.

Perform an SAP S/4HANA conversion including DMO.

Question 2

Which are valid options to check the progress of the database migration in a Microsoft Windows environment?

There is correct answers to this question.

Response:

Options:

A.

Check the "Charts Control Center" in the SUM UI

B.

Check logs for jobs starting with "RSUPG_SGEN" in the system

C.

Check the log files written under "SUM\abap\log"

D.

Check the dump size of the database export on disk

Question 3

You are performing an S/4HANA conversion of the development system. Which credentials do you use in which system to perform the adjustment of dictionary objects (SPDD)?

Please choose the correct answer.

Response:

Options:

A.

Credentials of a named user in client 000 of the shadow system

B.

Credentials of a named user in the development client of the development system

C.

Credentials of user DDIC in client 000 of the shadow system

D.

Credentials of user DDIC in the development client of the development system

Question 4

You downloaded content from the SAP note 1000009 ("ASU Toolbox 2008"). Which transaction needs to be executed to use that content in the ASU Toolbox?

Please choose the correct answer.

Response:

Options:

A.

/ASU/UPGRADE (Start ASU Toolbox in Upgrade Mode)

B.

/ASU/SSM (ASU Simple Schedule Manager)

C.

/ASU/SHOW_NOTE (Show SAP Note via Web-Browser)

D.

/ASU/START (Start ASU Toolbox)

Question 5

What phases of SUM will be executed during an SAP S/4HANA conversion including DMO?

There are 3 correct answers to this question.

Response:

Options:

A.

Phases DIFF*

B.

Phase DOWNCONF_DTTRANS

C.

Phase RUN_RSPTBFIL _ISUTABU

D.

Phases EU_IMPORT*

E.

Phase RUN_RSDBSCPY

Question 6

Unicode migration ECC on MaxDB to HANA in scale out what should we consider.

Options:

A.

Target DB size will increase temporarily

B.

A

C.

DMO can only be run with systems NW740 or NW731

Question 7

You have chosen the "Advanced" option during the main configuration of the SUM tool. Which steps take place via the shadow instance?

There are 2 correct answers to this question.

Response:

Options:

A.

Conversion of application tables (PARCONVJJPG)

B.

Activation of dictionary objects (ACT_UPG)

C.

Switch to new repository (EU_SWITCH)

D.

Modification adjustment (SPDD)

Demo: 7 questions
Total 53 questions