Question 1

Which tools does SAP Activate provide to support Guided Configuration? There are 3 answers to this question.

Options:

A.

Expert Configuration

B.

Self Service Configuration

C.

Model Company

D.

SAP Solution Composer

E.

Solution Builder

Question 2

Which key deliverable includes the development of RICEFW objects? Please choose the correct answer. Response:

Options:

A.

Enhancement Delivery

B.

Custom Extensions Management

C.

Sprint Execution

D.

Development Build

Question 3

What is the term used for workshops, which are intended to set value targets, validate SAP Standard functionality against customer requirements.

And collect delta requirements in the "New Implementation of SAP S/4HANA" transition path?

Options:

A.

Fit-to-Standard

B.

Delta Design

C.

Solution Validation

D.

Design Thinking

Question 4

What can cloud-centric customers do with SAP Cloud ALM?

Options:

A.

Manage the Intelligent Enterprise

B.

Update cloud releases

C.

Configure their cloud products

D.

Track cloud services

Question 5

In SAP Activate, what tool is used in the during the Realize phase to make forecasts based on actual data?

Options:

A.

Release Plan

B.

Burndown Chart

C.

Project Plan

D.

Product Increment

Question 6

From what can you generate tasks as follow-up to a fit-to-standard workshop?

Options:

A.

Process steps

B.

Business process value flows

C.

Notes

D.

Requirements

Question 7

Which of the following are part of the 10 SAP quality principle?

There are 2 correct answers to this question

Options:

A.

Start scoping early

B.

Use standard functionality optionally

C.

Achieve production readiness

D.

Plan phase at a time

Question 8

What are the elements in the SAP Activate Implementation Framework?

Options:

A.

Methodology

B.

Tools

C.

Content

D.

Analytics

Question 9

Which new role is introduced in the SAP activate methodology in a full scrum team?

Options:

A.

Project manager

B.

Product owner

C.

System administrator

D.

Application consultant

Question 10

What is the objective of a sprint retrospective meeting? Please choose the correct answer.

Options:

A.

Review and prioritize the backlog

B.

Improve the SCRUM process

C.

Define the stakeholder management approach

D.

Provide formal feedback to the project manager

Question 11

Your are defining the test strategy for your project. What would you include in a Scope of Integration test?

Options:

A.

the network communication

B.

the functionality of end-to-end business processes

C.

the functionality of modular processess

D.

the connectivity between database and application servers

Question 12

What are two important approaches, based on the Control Center concept that SAP proposes to use for streamlined implementation and operations within Premium Engagements? There are 2 correct answers to this

question.

Options:

A.

Run SAP Like a Factory

B.

Always Connected

C.

Intelligent Enterprise

D.

Build SAP Like a Factory

Question 13

What do you do during post cutover?

Options:

A.

Perform Technical System Test

B.

Perform the Verification Session of the SAP Going Live Check

C.

Conduct Organizational Readiness Check

D.

Setup Operational Support

Question 14

How can the project manager help to keep momentum in the project and help to keep the customer involved?

Options:

A.

Increase the number of Q-Gates

B.

Add customer resources to the project to reduce the need for formal training

C.

Leverage agile cycles to build and test the solution

D.

Walk through the solution processes with the stakeholders

Question 15

In which phase do you run the user acceptance test?

Options:

A.

Build and Test

B.

Final Preparation

C.

Deploy

D.

Realize

Question 16

Which criterion does the Product Owner use to sequence the product backlog? Please choose the answer.

Options:

A.

Complexity

B.

Relative effort

C.

Resource availability

D.

Business priority

Question 17

Which of the following types of monitoring are part of SAP Cloud ALM for operations? Note: There are 2 answers to this question.

Options:

A.

Business process monitoring

B.

Event and alert monitoring

C.

Business user monitoring

D.

Integration and exception monitoring

Question 18

What are some activities in the Requirement-to-deploy scenario within SAP Solution Manager? NOTE: There are 2 Correct Answers to this question.

Options:

A.

Walkthrough for Wave

B.

Demo for Sprint

C.

User Acceptance Test every Sprint

D.

SAP Model Company demo for every wave

Question 19

Who determines the priority of user stories in the backlog of an Agile project?

Options:

A.

Project Team

B.

SCRUM Master

C.

Project Manager

D.

Product Owner

Question 20

Which enhancements to SAP Cloud ALM are planned for the future? Note: There are 2 answers to this question.

Options:

A.

Process scope

B.

Product coverage

C.

Task coverage

D.

Functional scope

Question 21

What are some goals of the Fit-to-Standard workshops?

Options:

A.

To identify relevant data migration objects.

B.

To review the SAP Best Practices in the starter system.

C.

To identify customer-defined configuration changes within the scope of the service.

D.

To define the Integration and API List for the solution.

E.

To gather input for customer-defined customizations to the solution.

Question 22

What kind of user is enabled by SAP Cloud ALM for operations to identify disruptions and react to them? Note: There are 2 answers to this question.

Options:

A.

Line of business user

B.

Reference user

C.

Communication user

D.

IT user

E.

End user

Question 23

How many change projects can be active at a time?

Options:

A.

1

B.

4

C.

3

D.

2

Question 24

Which core capability of SAP Cloud ALM for implementation supports the management of the requirements lifecycle?

Options:

A.

Change and Deployment Management

B.

Test Management

C.

Task Management

D.

Process Management

Question 25

Which of the following are levels in the structure of an SAP Best practices solution package? There are 2 answers to this question.

Options:

A.

Configuration guides

B.

Building blocks

C.

Scope items

D.

Business process scenarios