Summer Special Flat 65% Limited Time Discount offer - Ends in 0d 00h 00m 00s - Coupon code: suredis

SAP C_TS422_2023 SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Exam Practice Test

Demo: 24 questions
Total 80 questions

SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Questions and Answers

Question 1

In the Capacity Scheduling Table, which settings can you select for the planning strategy?

Note: There are 3 correct answers to this question.

Options:

A.

Finiteness level

B.

Fixed pegging

C.

Scheduling control

D.

Planning mode

E.

Direction

Question 2

Why would you use phantom assemblies? Note: There are 3 correct answers to this question.

Options:

A.

To increase the number of planning levels

B.

To simplify the structure of bills of material

C.

To reduce the number of material masters

D.

To make the assignment of components easier

E.

To reduce the number of changes required in bills of material

Question 3

How can you set up a material as a phantom assembly?

Note: There are 2 correct answers to this question

Options:

A.

Define the special procurement type inside the material master.

B.

Change the item category of the phantom assembly in the bill of material •—' (BOM)

C.

Define the special procurement type inside the BOM

D.

Change the phantom item indicator for the phantom assembly in the bill of material (BOM)

Question 4

In documentation for MRP in Advanced Planning, you read that new orders are created through infinite planning. What does this mean for the capacity requirements of a new order?

Options:

A.

MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.

B.

MRP assigns the capacity requirements automatically after the last scheduled order on a work center.

C.

MRP creates the capacity requirements without checking the work center capacities.

D.

MRP creates the capacity requirements only if the work center has sufficient capacity.

Question 5

Which materials have a negative quantity in a bill of material or in a recipe?

Note: There are 3 correct answers to this question

Options:

A.

Continuous flow materials

B.

Bulk materials

C.

By-products

D.

Co-products

E.

Waste products

Question 6

What does forecasting in the demand planning cycle include?

Note: There are 3 correct answers to this question

Options:

A.

One-off events

B.

Past quotation quantities

C.

Past sales order quantities

D.

Market intelligence

E.

Past production planning quantities

Question 7

If the stock level drops below the reorder stock in reorder point planning, what logic would the system use to trigger procurement?

Options:

A.

Fill up to the maximum stock level.

B.

Fill up to the safety stock level.

C.

Fill up based on the lot size procedure.

D.

Fill up to the reorder stock level.

Question 8

Which time elements can be reduced by a reduction strategy?

Note: There are 3 correct answers to this question.

Options:

A.

Goods receipt processing time

B.

Move time

C.

Wait time

D.

Float after production

E.

Queue time

Question 9

where does the system check master data selection settings during the creation of planned orders and production orders?

Note: There are 3 Correct answers to this question.

Options:

A.

in the bill of material (BOM)

B.

in the work centers

C.

in the MRP controller

D.

In the routing

E.

in the production version

Question 10

You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

Options:

A.

Kanban

B.

Material requirements planning

C.

Backflushing

D.

Production order release

Question 11

Your company manufactures materials whose specifications differ for each manufacturing process. Which application do you have to use in SAP S/4HANA to be able to track and use this information in all areas of logistics?

Options:

A.

Engineering change management

B.

Quality management

C.

Process order management

D.

Batch management

Question 12

For a production version to be valid and consistent, what requirements must be fulfilled? Note: There are 3 correct answers to this question.

Options:

A.

The deletion flag must NOT be set for the bill of material (BOM) or the routing

B.

The lot size range must be within the lot size range of the assigned routing.

C.

The assigned routing and bill of material (BOM) must be valid in the entirevalidity period.

D.

The assigned routing must be a rate routing.

E.

The assigned routing must NOT have alternative sequences

Question 13

Which information is required when you create a product master in SAP S/4HANA?

Note: There are 2 correct answers to this question.

Options:

A.

Product type

B.

Selection screen for views

C.

Selection screen for plants

D.

Base unit of measure

Question 14

Which of the following questions do you have to answer before you start creating a bill of material (BOM)?

Options:

A.

Is the material type allowed in the BOM?

B.

Which base unit of measure does the material have?

C.

What status does the BOM have?

D.

In which storage location is the BOM required?

Question 15

Which business processes are affected by settings in the order-type-dependent parameters?

Note: There are 2 correct answers to this question.

Options:

A.

Check material availability.

B.

Schedule production orders.

C.

Define integration with cost accounting.

D.

Select master data.

Question 16

Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?

Options:

A.

Use a propagation range.

B.

Use a resource group

C.

Use a planning area.

D.

Use a planning group.

Question 17

What is the difference between co-products and by-products?

Options:

A.

Only co-products are identified by a special item category in the bill of material (BOM)

B.

Only co-products can be manufactured in isolation from the main product

C.

Only co-products have a zero inventory valuation

D.

Only co-products appear in the process or production order settlement rule

Question 18

You want to trigger in-house production of a semi-finished material before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?

Options:

A.

Planning with final assembly (40)

B.

Production by lot size (30)

C.

Planning at assembly level (70)

D.

Make-to-order production (20)

Question 19

How can you characterize dependent requirements in material requirements planning?

Note: There are 2 correct answers to this question.

Options:

A.

They are created with exact times in Advanced Planning.

B.

They are created when an independent requirement is created for the finished product.

C.

They are created on assembly level during the planning run.

D.

They are only created for multilevel bill of material (BOM) structures

Question 20

Which master data object governs the relationship between supply source and demand source in the Kanban process?

Options:

A.

Replenishment strategy

B.

Production supply area

C.

Control cycle

D.

Rate routing

Question 21

Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks?

Note: There are 2 correct answers to this question.

Options:

A.

Use the Batch Information Cockpit.

B.

Use batch derivation.

C.

Use batch determination

D.

Use the batch where-used list.

Question 22

Which options do you have to plan both quantities and capacities during line loading in repetitive manufacturing?

Note: There are 2 Correct answers to this question?

Options:

A.

Run MRP with quota arrangement

B.

Run PP/DS heuristic for repetitive manufacturing

C.

Assign planned orders manually in the planning table

D.

Assign planned orders manually in the planning table

Question 23

Which time elements are relevant for lead time scheduling of a production order? Note:

There are 2 correct answers to this question.

Options:

A.

setup time

B.

Opening Period

C.

Float after Production

D.

Total replenishment lead time

Question 24

How can a material availability check be triggered automatically for a production order?

Note: There are 2 correct answers to this question.

Options:

A.

By capacity planning

B.

By mass processing

C.

By order release

D.

By order confirmation

Demo: 24 questions
Total 80 questions