The settings for MRP can be maintained at different levels. If settings have been maintained in different places, in which sequence does the system search for the MRP settings? Please choose the correct answer.
Before a user can add multiple production versions in a material master, what information should be collected?
There are 3 correct answers to this question.
Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks?
A customer is considering switching from order-related settlement to productrelated settlement. What are capabilities of cost collectors? There are 2 correct answers to this question.
You want to integrate an existing planned order into Advanced Production Planning. Which report do you use? Please choose the correct answer.
Which task list types can have parallel sequences? There are 2 correct answers to this question.
You want to set up a make-to-order planning scenario for a finished material. Some components from the bill of materials (BOM) should be procured per sales order, other components should be procured for various requirements. Fore casting is NOT possible. Which settings do you make to achieve this?
MRP created a planned order for a material that has one single material from stock as a component. What happens to this dependent requirement when you convert the planned order into a production order?
Which options are available for an SAP S/4HANA deployment? There are 2 correct answers to this question.
What is the purpose of a reporting point confirmation in repetitive manufacturing? Note: There are 2 correct answers to this question.
What determines whether the planned independent requirements in MRP consume other requirements?
What does the industry sector determine? Note: There are 2 correct answers to this question.
In your project, you have several materials that are planned by different people. How can you assign the planning responsibility?
You want to represent setup time as a graphical object in the Detailed Scheduling Planning Board. Which actions are needed? There are 2 correct answers to this question.
If the stock level drops below the reorder stock in reorder point planning, what is the system logic to trigger procurement?
How can you set up the supply source for the SAP Kanban process? Note: There are 3 correct answers to this question.
What are properties of MRP Live? There are 2 correct answers to this question.
Your project uses process orders for the production of liquid chemicals. What can you define to ensure that the production flow happens only in physically connected tanks?
What does the bill of material usage (BOM usage) control at the BOM item level? There are 2 correct answers to this question.
You want to triggering-house production of a semi-finished mater al before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?
Which of the following functions can be performed when the production order has the status "Created" (CRTD)? Please choose the correct answer.
Which of the following time elements does MRP use during backward scheduling
for in-house production?
There are 2 correct answers to this question.