New Year Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

PMI PMI-PBA PMI Professional in Business Analysis Exam Practice Test

Demo: 60 questions
Total 200 questions

PMI Professional in Business Analysis Questions and Answers

Question 1

A business analyst created requirements for production of a product extract file for several systems. After reviewing the complex systems and dividing the processes into manageable tasks, the business analyst is able to identify the tasks required to implement the deliverable.

Which analysis technique has the business analyst used?

Options:

A.

Organization

B.

Decomposition

C.

Dependency

D.

Interface

Question 2

Once a new project has been identified, the business analyst works with project team members to define what will be included in and excluded from the new system. Which of the following has the business analyst defined?

Options:

A.

Solution design

B.

Business requirements

C.

Solution scope

D.

Business case

Question 3

A system enhancement project has been initiated to address the concerns of an external group of stakeholders not included in the first release. What should be done to ensure stakeholder satisfaction with the enhancement?

Options:

A.

Request that the project manager identify all affected project stakeholders.

B.

Provide all signed-off project documentation to the stakeholders for information purposes only.

C.

Engage all stakeholders early in the requirements gathering phase to define acceptance criteria.

D.

Solicit feedback and add requirements to the project backlog.

Question 4

The requirements traceability matrix should primarily be used to:

Options:

A.

identify the risks associated with dependent requirements.

B.

define a convention to map the requirements to their sources.

C.

ensure that all requirements have been met.

D.

address the responsibility owner for each requirement.

Question 5

A company has completed a major project within time, cost, and scope and satisfied high-level quality standards and marketing requests. However, the product was considered a complete failure by shareholders and the market due to low return on investment.

From the business analysis perspective, the main reason for this business failure was a failure to:

Options:

A.

set the product positioning.

B.

review and evaluate market expectations.

C.

gather the appropriate usability requirements.

D.

establish measurable success criteria in the business case.

Question 6

A business analyst is ready to begin requirements elicitation; however, stakeholders are not available to participate for another two weeks. Which elicitation technique should the business analyst use during this time?

Options:

A.

Cost-benefit analysis

B.

Benchmarking

C.

Brainstorming

D.

Document analysis

Question 7

After completing the requirements, the project manager and business analyst realize that the project scope is not feasible in the projected schedule. The business analyst needs to review the amount of work the team is capable of delivering based on the approved project schedule.

Which prioritization technique should the business analyst use?

Options:

A.

Time-boxing

B.

SWOT analysis

C.

Weighted ranking

D.

Multivoting

Question 8

The following requirement was included in a business requirements document: “An API shall be built to send data back and forth from the accounting system to the customer relationship system so that name and address data can be synchronized.” What should be done with this business requirement?

Options:

A.

It should remain because it specifies the reason why the business requirement is needed.

B.

It should be removed because it does not state how often the data should be synchronized.

C.

It should be revised because it states a solution to the problem rather than the business need.

D.

It should remain because it specifies the type of data and the source system.

Question 9

A company has developed a new product for a customer. The customer provided a specification, but the company did not produce the system requirements in the verification matrix.

The customer is having difficulty determining if the product is meeting the requirements during the test event because the:

Options:

A.

customer did not adequately review the test procedure before the test.

B.

test engineer is not communicating effectively with the customer.

C.

requirements in the technical specification are unclear and ambiguous.

D.

customer cannot make this determination until the entire test is complete.

Question 10

The business analyst wants to ensure that requirement changes can be formally tracked after the product is baselined. What will the business analyst need to evaluate the proposed change?

Options:

A.

Requirements management plan

B.

Impact analysis

C.

Scope statement

D.

Pareto analysis

Question 11

How should a business analyst determine whether a solution satisfies business requirements?

Options:

A.

By reviewing the results of user acceptance testing

B.

By evaluating the solution against the project charter

C.

By conducting a brainstorming session with end users

D.

By reviewing the traceability matrix

Question 12

The business analyst has completed the requirements gathering and documentation processes in developing a baseline document. Several signoffs are needed. During the joint review process with the key stakeholders, the stakeholders announce that they are still not ready to sign off due to a communication gap.

Which technique should the business analyst have followed to ensure consensus?

Options:

A.

The business analyst should have performed a complete review of each requirement with one of the stakeholders’ peers before the meeting.

B.

The business analyst should have performed a complete review of each requirement with the key stakeholders prior to the meeting.

C.

The business analyst should have reviewed the requirements of the project sponsor first before reviewing other requirements.

D.

The business analyst should have invited the key stakeholders to the meeting.

Question 13

A sponsor requests a new requirement. The business analyst explains that most of the information needed for this requirement does not exist and that the requirement cannot be implemented. The business analyst recommends deferring the requirement until the needed information is available and then adding it to a subsequent project. The sponsor agrees.

What should the business analyst do next?

Options:

A.

Bring the subsequent project to the change control board (CCB).

B.

Ask the stakeholders to review the requirement before any other action is taken.

C.

Communicate that the status of this requirement has changed.

D.

Mark the requirement as complete so that it is not forgotten.

Question 14

Which solution should be chosen according to the completed weighted-ranking matrix?

Options:

A.

Outsource the development.

B.

Purchase off-the-shelf software.

C.

Develop in-house software.

D.

Enhance the existing system.

Question 15

The project sponsor needs to know which requirements will be implemented. Which of the following would be the most valuable for a business analyst to provide?

Options:

A.

Requirements traceability matrix

B.

Requirements baseline document

C.

Requirements management plan

D.

Requirements impact analysis

Question 16

A business analyst has been assigned to a project that will design and build two new bridges and, at the same time, redesign a failing bridge for a local structural engineering company. All three bridges must be constructed and meet all safety requirements before flood season next spring.

How would the business analyst define the scope of this project?

Options:

A.

Perform a work breakdown structure.

B.

Perform a feasibility study.

C.

Perform process modelling.

D.

Perform a structured walkthrough.

Question 17

A startup company sells organic vegetable and fruit smoothies. Management is tracking a rapid decrease in sales of their best-selling juice, so they contract a business analyst to identify solutions in order to increase sales by comparing similar products offered by competitors.

Which technique or tool should be used?

Options:

A.

Competitive analysis

B.

Benchmarking

C.

Trend analysis

D.

Focus group

Question 18

Which of the following is the best approach to enable developers and product owners to be in constant communication so that changes or issues that occur during development are exposed and discussed as they develop?

Options:

A.

Iterative

B.

Waterfall

C.

Linear

D.

Agile

Question 19

Which technique or tool is used to obtain acceptance of the delivered product?

Options:

A.

Expert judgment

B.

Facilitated workshops

C.

Inspection

D.

Contextual inquiry

Question 20

The project manager is beginning to prepare for a test readiness review with the customer. The project manager knows that the customer will want a summary of requirements that have been rejected or deferred. The project manager has requested that the business analyst provide a list of rejected and deferred requirements.

What should the business analyst have done to complete this request?

Options:

A.

A Set up a change control board to track the number of rejections.

B.

Limit the number of rejected requirements on the project.

C.

Track rejected requirements in the system requirements verification matrix.

D.

Spend more time up-front reviewing the requirements to limit rejections.

Question 21

In the first few weeks after a large implementation of a new web-based application, a critical report failed. Further Investigation determined that a worker had been using a field that was not supposed to be used. This issue was not identified in testing.

Which technique could have prevented this problem from occurring?

Options:

A.

Prototyping

B.

Diagrams

C.

Use cases

D.

Document analysis

Question 22

The software developers have delivered a completed solution. The quality assurance team has passed the solution. What should the business analyst do next?

Options:

A.

Evaluate the solution against the project charter.

B.

Conduct user acceptance testing.

C.

Evaluate the solution with the sponsor(s).

D.

Conduct performance testing.

Question 23

Which of the following techniques contrasts the current and desired business views to analyze possible business changes?

Options:

A.

Impact analysis SWOT analysis

B.

SWOT analysis

C.

Gap analysis

D.

Trend analysis

Question 24

A business analyst is attempting to elicit requirements on a current project. The business subject matter experts (SMEs) from various departments in the company question how the solution will work with their various systems. Which modeling technique should the business analyst use to depict how the solution will work with all of the company's systems?

Options:

A.

Data modeling

B.

B. Interface modeling

C.

Rules modeling

D.

Enterprise modeling

Question 25

A business analyst is preparing a requirements management plan and needs to define a method to deal with a complex project with stakeholders who find it difficult to articulate their needs. Which method would best minimize requirements risk?

Options:

A.

Questionnaires

B.

Group decision making

C.

Stakeholder analysis

D.

Prototyping

Question 26

Which statement accurately depicts what changes can be made to requirements after they are baselined?

Options:

A.

Requirements can be changed only with sponsor approval.

B.

Requirements can be changed through a defined process.

C.

Requirements cannot be changed once development begins.

D.

Requirements cannot be changed once user acceptance testing begins.

Question 27

After implementation of the product, the customer reports defects. What is the best course of action to take?

Options:

A.

Compare reported defects with user acceptance test results.

B.

Escalate the issue to the project manager since the acceptance was given by the customer.

C.

Do nothing since the solution is now the responsibility of the operations manager.

D.

Involve the end users and plan a new round of acceptance tests to check the gaps.

Question 28

Which of the following is a method for requirements change control?

Options:

A.

Communication management

B.

Scope analysis

C.

Requirements management

D.

Baselining

Question 29

Midway through the requirements gathering phase, a stakeholder informs the business analyst that a requested requirement does not address the solution. The stakeholder wants to know who made the request. The business analyst spends hours searching emails to identify the requestor.

What should the business analyst have documented?

Options:

A.

Sponsor approval in the requirements traceability matrix

B.

The source in the RACI matrix

C.

Roles and responsibilities in the RACI matrix

D.

The source in the requirements traceability matrix

Question 30

Which of the following can be used to determine if requirements align to the product's objectives?

Options:

A.

Five Whys

B.

Activity network diagrams

C.

Context diagrams

D.

Business use cases

Question 31

A business analyst has been assigned to a project team that is redesigning the company's website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.

Which type of requirements are these?

Options:

A.

In-scope

B.

Tested

C.

Implemented

D.

Out-of-scope

Question 32

A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting. The stakeholder insists that these requirements must be taken into account despite time and budget constraints.

What is the most effective way to manage this situation?

Options:

A.

Discuss the change with stakeholders during the baseline approval meeting and ask them to approve the new baseline.

B.

Ask for more resources to manage this change and justify these additional resources with the value the change will give to

the company.

C.

Share the new requirements with all stakeholders and ask them to submit their comments before the meeting.

D.

Postpone the baseline approval meeting, analyze the impact, and schedule a new meeting to discuss dependencies and

priorities with stakeholders.

Question 33

After reviewing a business case, project goals, and objectives, a business analyst determines that the organization prefers taking an exploratory approach to finding the solution that best meets the business need. Which approach best aligns with the business need for this organization?

Options:

A.

Plan-driven approach

B.

Waterfall approach

C.

Analytical approach

D.

Change-driven approach

Question 34

A new project is in the planning phase. The business owner believes that, since the timeline is aggressive, requirements elicitation should begin as soon as possible.

Which activity should the business analyst initiate before beginning requirements elicitation?

Options:

A.

Prepare the requirements traceability matrix.

B.

Define how the solution will be evaluated.

C.

Draft a high-level data model.

D.

Document how the relevant systems interact.

Question 35

During a requirements workshop, sponsors and managers from different departments express varying points of view and priorities about the product's functions and requirements. The business analyst struggles with facilitating the group to reach an agreement.

What should the business analyst have defined to avoid this?

Options:

A.

Communications approach in the business analysis plan

B.

Decision-making process in the project management plan

C.

Decision-making process in the business analysis plan

D.

Communications approach in the project management plan

Question 36

An organization is in the process of replacing its current system. The business analyst is charged with ensuring that all current connections to other systems remain functional after the upgrade.

What analysis should the business analyst conduct to facilitate a successful migration?

Options:

A.

Document

B.

User interface

C.

Interface

D.

Systems

Question 37

Last year, a company registered a high number of complaints about its customer service. Which of the following tools or techniques can help to identify the high-priority changes needed to improve that service?

Options:

A.

A work breakdown structure analysis of the service

B.

A Pareto analysis

C.

A flowchart of the service

D.

A cause-and-effect diagram

Question 38

The business analysts have concluded a requirements elicitation workshop. They now need to define rationale for each requirement.

Which of the following pairs of items would be important to include in the rationale?

Options:

A.

Reasons and assumptions

B.

Product vision and operational relationships

C.

Stakeholder impact and design decisions

D.

Functional relationships and work breakdown structure code

Question 39

For a large, highly complex project with significant risk, which elicitation technique should be used to analyze input to and output from the product?

Options:

A.

System analysis

B.

Dependency analysis

C.

Risk analysis

D.

Interface analysis

Question 40

Two weeks prior to the delivery date, a customer changes the business requirements. What should the business analyst do?

Options:

A.

Deliver the existing product and then begin work on the requested changes.

B.

Trace the requirements and measure the impact of the requested changes on the existing delivery date.

C.

Schedule a review by the change control board (CCB) to determine next steps.

D.

Ask the developers to implement the changes.

Question 41

During the initial phase of a project, which technique could assist in identifying and categorizing the stakeholders?

Options:

A.

Business activity model

B.

RAC! matrix

C.

Power/interest grid

D.

Organization modeling

Question 42

Requirements elicitation for a project is occurring. The marketing, acquisition, and production departments want to include specific requirements. The CEO has a requirement to deploy in three months.

Which of the following actions will have a greater influence on the project success?

Options:

A.

Prioritize and develop the requirements of the marketing department since the project will impact a greater number of people.

B.

Estimate the effort required for each requirement and develop as many functionalities as possible.

C.

Conduct a stakeholder analysis and balance requirements by understanding the relative power associated with each stakeholder group.

D.

Explain the situation to the CEO and try to obtain an extension of the contract for the actual time necessary to develop the system.

Question 43

Company A has set aside capital to invest in an upgrade to their scheduling system. Documentation of the current structure was presented to the business analyst. However, the description of certain steps is not documented clearly, and the business analyst has not been allowed to inspect the existing system. During elicitation, the business analyst asked questions of the schedulers as they performed functions in order to gain an understanding of the process.

Which type of elicitation technique did the business analyst use in this instance?

Options:

A.

Active observation

B.

Participatory observation

C.

Interview

D.

Simulation

Question 44

Company A has initiated a project to update their online ordering system. The business analyst has noticed that the purchasing department, a primary stakeholder, is excluded from the list of stakeholders.

In which reference material can the business analyst find information about the missing project stakeholders?

Options:

A.

Organizational chart

B.

Business case

C.

Business analysis plan

D.

Business analyst communication plan

Question 45

A project was in the design phase when the team received news of a new regulatory mandate that affects the project. The requirements have already been approved and baselined. If the new requirements are not included, the company will be out of compliance and may

face monetary penalties.

What should the business analyst do next?

Options:

A.

Obtain approval from the project manager.

B.

Define the project scope.

C.

Follow the change control process.

D.

Update the requirements.

Question 46

A business analyst is working on a system enhancement project and has completed the requirements according to the requirements management plan. The business analyst is now ready to request approval from the stakeholders.

How should the business analyst obtain approval?

Options:

A.

Conduct a formal or informal review of the requirements.

B.

Create and maintain an audit history log of changes to requirements.

C.

Provide a defect tracking log for review.

D.

Send an email requesting approval of requirements.

Question 47

A company is in the final phases of implementing a project for a client. Which tool or technique could the business analyst use to iteratively validate the solution?

Options:

A.

Expected vs. actual results

B.

Expected vs. actual costs

C.

Schedule variance

D.

Quality variance

Question 48

The customer and the business analyst are collaborating in the development of a solution scope. It is important for the customer to:

Options:

A.

communicate changes to requirements only when they are completely defined.

B.

spend the time required to provide, clarify, and elaborate requirements.

C.

challenge assessments of the cost and feasibility of requirements.

D.

perform an alternatives analysis for requirements implementation.

Question 49

A business analyst has captured all of the requirements from the various stakeholders within the organization and has compiled them into a complete list. After reviewing the list of requirements with the stakeholders, it is determined that the list of requirements is too large and will exceed the allotted budget.

Which tool or technique should the business analyst use with the stakeholders to prioritize the requirements to determine which requirements are approved, deferred, or rejected?

Options:

A.

SMART Goals

B.

Moscow Analysis

C.

SWOT Analysis

D.

Timeboxing Analysis

Question 50

During validation of a project solution, the business analyst discovers that a requirement has been altered. Instead of placing the company logo in the upper-left corner of the window, it is displayed in the upper-right corner. When the business analyst asks the developer about the change, the developer says that one of the stakeholders asked directly for the change.

Which corrective action should the business analyst take?

Options:

A.

Ask the developer to correct the logo as stated in the requirement.

B.

Confront the stakeholder that requested the change.

C.

Follow the change control process as defined in the business analysis plan.

D.

Discuss the change in the next stakeholder meeting.

Question 51

The customer generated a design specification for a new product. What is the best action to take to establish an approved requirements baseline with the customer?

Options:

A.

Create a requirements traceability matrix for review and approval by the customer.

B.

Create a requirements baseline approval form for the customer to review and approve.

C.

Request that the customer create a baseline of the requirements in the contract specification.

D.

Perform a variance analysis on the design specification and report the results to the customer.

Question 52

A financial company deployed a new online product to their customers to invest in the stock market. The company notices a problem regarding financial calculations and starts the problem analysis. The company discovers that the new rules for taxes and fees were not implemented.

This problem could have been avoided by:

Options:

A.

using a table that shows each applicable business rule with the implemented functional requirement.

B.

implementing an automated issue tracking system to facilitate the tracing of defects to the requirements.

C.

involving a business analyst during all phases of system development.

D.

rolling back the operations using a contingency process in order to avoid loss and client dissatisfaction.

Question 53

A business analyst is developing a traceability matrix to determine whether or not any gaps exist and to identify any discrepancies.

Which critical field is needed to ensure that the traceability matrix is usable?

Options:

A.

Status

B.

Hierarchy

C.

Owner

D.

Requirements description

Question 54

When a business analyst uses subject matter experts to define roles and identify influencers, which project artifact is created or updated?

Options:

A.

Stakeholder register

B.

RACI matrix

C.

SWOT analysis

D.

Stakeholder management plan

Question 55

Which document best provides the boundaries for product development?

Options:

A.

Scope definition

B.

Requirements baseline

C.

Project plan

D.

Scope document

Question 56

A type of requirements document that would be the most valuable to a database administrator would be:

Options:

A.

a data flow diagram.

B.

a business process diagram.

C.

an entity relationship diagram.

D.

an object diagram.

Question 57

The quality function deployment is best suited to assist in the process of:

Options:

A.

relating the product features to customer value.

B.

quality control by determining the control charts and the run charts.

C.

quality assurance by structuring the quality audits.

D.

controlling the effects between the quality functions.

Question 58

A firm implements SharePoint and the business analyst creates the requirements to develop a business analysis repository. In the requirements, the analyst describes a detailed workflow that includes appropriate stakeholders receiving email notifications of certain activities. The SharePoint team needs to know which activities should trigger the notification workflow.

Which workflow trigger should the business analyst incorporate?

Options:

A.

Any change to the requirements matrix

B.

Changes to test cases traced to requirements

C.

Change through project life cycle

D.

Changes to stakeholder memberships

Question 59

Which of the following actions will contribute most to the success of the initial stage of the project?

Options:

A.

Interview stakeholders to clearly define the problem.

B.

Document the requirements and obtain sign-off.

C.

Establish the change control process of the project.

D.

Define the acceptance criteria required during the acceptance phase.

Question 60

Company A would like to enter into a new market. The business analyst has been assigned to a project for which nobody in Company A has any prior experience. The project manager has asked the business analyst to assist in resource planning.

What should the business analyst recommend to the project manager?

Options:

A.

Ask the developer's team manager for more resources.

B.

Review the business case to reconsider the project.

C.

Hire external subject matter experts for the core project team.

D.

Ask the sponsor for more resources.

Demo: 60 questions
Total 200 questions