New Year Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

PMI PMI-001 Project Management Professional v5 Exam Practice Test

Demo: 137 questions
Total 918 questions

Project Management Professional v5 Questions and Answers

Question 1

Which is a tool used in monitoring and controlling project work?

Options:

A.

Work performance information

B.

Project management information system (PMIS)

C.

Activity duration estimates

D.

Scheduled network analysis

Question 2

What is an objective of the Developing Project Team Process?

Options:

A.

Feelings of trust and improved cohesiveness

B.

Ground rules for interaction

C.

Enhanced resource availability

D.

Functional managers become more involved.

Question 3

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

Options:

A.

Cost variance (CV)

B.

Cost performance index (CPI)

C.

Budget at completion (BAC)

D.

Variance at completion (VAC)

Question 4

In Project Cost Management, which input is exclusive to the Determine Budget process?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

Project schedule

D.

Resource calendars

Question 5

Perform Quality Control is accomplished by:

Options:

A.

Identifying quality standards that are relevant to the project and determining how to satisfy them.

B.

Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.

C.

Ensuring that the entire project team has been adequately trained in quality assurance processes.

D.

Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.

Question 6

Which standard examines an enterprise’s project management process capabilities?

Options:

A.

PMBOK Guide

B.

The Standard for Program Management

C.

Organizational Project Management Maturity Model “OPMJ

D.

The Standard for Portfolio Management

Question 7

Cost aggregation is typically performed by aggregating work packages in accordance with the:

Options:

A.

Program evaluation and review technique (PERT).

B.

Cost of quality (COQ).

C.

Rough order of magnitude (ROM).

D.

Work breakdown structure (WBS).

Question 8

Plan-do-check-act is also known as:

Options:

A.

prevention over inspection.

B.

statistical sampling.

C.

management responsibility,

D.

continuous improvement.

Question 9

Funding limit reconciliation is a tool and technique used in which process?

Options:

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Control Budget

Question 10

When cost variance is negative and schedule variance is positive, the project is:

Options:

A.

under budget and behind schedule.

B.

over budget and ahead of schedule.

C.

on schedule.

D.

complete; all planned values have been earned.

Question 11

Plan Schedule Management is a process in which Knowledge Area?

Options:

A.

Project Scope Management

B.

Project Human Resource Management

C.

Project Integration Management

D.

Project Time Management

Question 12

Which process in Project Time Management includes reserve analysis as a tool or technique?

Options:

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

Question 13

The total of the planned value (PV) is also known as:

Options:

A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Question 14

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Question 15

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

Options:

A.

Human resource management plan.

B.

Activity resource requirements.

C.

Personnel assessment tools,

D.

Multi-criteria decision analysis.

Question 16

Whose approval may be required for change requests after change control board (CCB) approval?

Options:

A.

Functional managers

B.

Business partners

C.

Customers or sponsors

D.

Subject matter experts

Question 17

Which of the following is a schedule network analysis technique that takes limited resources into account?

Options:

A.

Network reserve analysis

B.

Critical chain method

C.

Lead and lag adjustment

D.

Critical path method

Question 18

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

Options:

A.

Critical path method

B.

Variance analysis

C.

Schedule compression

D.

Schedule comparison bar charts

Question 19

Labor, materials, equipment, and supplies are examples of:

Options:

A.

Resource attributes.

B.

Resource types.

C.

Resource categories.

D.

Resource breakdown structures (RBS).

Question 20

What is the difference between the critical path and the critical chain?

Options:

A.

Scope changes

B.

Resource limitations

C.

Risk analysis

D.

Quality audits

Question 21

Which tool or technique is used in the Perform Integrated Change Control process?

Options:

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

Question 22

What is the minimum a project schedule must include?

Options:

A.

Variance analysis

B.

A planned start date and a planned finish date for each schedule activity

C.

A critical path diagram

D.

Critical chain analysis

Question 23

A collection of projects managed as a group to achieve strategic objectives is referred to as a:

Options:

A.

plan

B.

process

C.

program

D.

portfolio

Question 24

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

Options:

A.

0.50

B.

0.67

C.

1.50

D.

2.00

Question 25

An output of the Develop Project Team process is:

Options:

A.

Organizational process assets.

B.

Enterprise environmental factors updates.

C.

Project staff assignments.

D.

Organizational charts and position descriptions.

Question 26

Which of the following events would result in a baseline update?

Options:

A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.

B.

A customer has approved a change request broadening the project scope and increasing the budget.

C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.

D.

One of the key project team resources has left the team and no replacement is available.

Question 27

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Options:

A.

Cost baseline

B.

Cost forecasting

C.

Cost variance

D.

Cost budgeting

Question 28

When does Monitor and Control Risks occur?

Options:

A.

At project initiation

B.

During work performance analysis

C.

Throughout the life of the project

D.

At project milestones

Question 29

When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

Options:

A.

improvement

B.

program

C.

result

D.

portfolio

Question 30

PMBOI Guide is a standard that describes:

Options:

A.

product-oriented processes.

B.

project management processes.

C.

product-oriented and project management processes.

D.

program management and project management processes.

Question 31

The formal and informal interaction with others in an organization industry, or professional environment is known as:

Options:

A.

negotiation

B.

organizational theory

C.

meeting

D.

networking

Question 32

In which type of organizational structure are staff members grouped by specialty?

Options:

A.

Functional

B.

Projectized

C.

Matrix

D.

Balanced

Question 33

The component of the risk management plan that documents how risk activities will be recorded is called:

Options:

A.

tracking

B.

scoping

C.

timing

D.

defining

Question 34

The scope of a project cannot be defined without some basic understanding of how to create the specified:

Options:

A.

objectives

B.

schedule

C.

product

D.

approach

Question 35

Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?

Options:

A.

Project Time Management

B.

Project Cost Management

C.

Project Scope Management

D.

Project Human Resource Management

Question 36

Which of the following investigates the likelihood that each specific risk will occur?

Options:

A.

Risk register

B.

Risk audits

C.

Risk urgency assessment

D.

Risk probability and impact assessment

Question 37

Which of the following is a tool and technique used in the Develop Schedule process?

Options:

A.

Three-point estimates

B.

Resource leveling

C.

Precedence diagramming method

D.

Bottom-up estimating

Question 38

Within a matrix organization, dual reporting of team members is a risk for project success. Who is responsible for managing this dual reporting relationship factor?

Options:

A.

Functional manager

B.

Project manager

C.

Functional manager supported by the project manager

D.

Project management office

Question 39

Scope verification is PRIMARILY concerned with which of the following?

Options:

A.

Acceptance of the work deliverables.

B.

Accuracy of the work deliverables.

C.

Approval of the scope statement.

D.

Accuracy of the work breakdown structure.

Question 40

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

Options:

A.

Project management plan.

B.

Project charter.

C.

Work breakdown structure.

D.

Stakeholder register.

Question 41

The Verify Scope process is primarily concerned with:

Options:

A.

formalizing acceptance of the completed project deliverables.

B.

accuracy of the work deliverables.

C.

formalizing approval of the scope statement.

D.

accuracy of the work breakdown structure (WBS).

Question 42

An input required to develop a preliminary project scope statement is:

Options:

A.

Organizational Structure

B.

Organizational Process Assets

C.

Organizational Matrix

D.

Organizational Breakdown Structures

Question 43

Which element does a project charter contain?

Options:

A.

Management reserves

B.

Work breakdown structure

C.

Stakeholder list

D.

Stakeholder register

Question 44

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

Options:

A.

Plan Stakeholder Management

B.

Identify Stakeholders

C.

Manage Stakeholder Engagement

D.

Control Stakeholder Engagement

Question 45

Risk responses reflect an organization's perceived balance between:

Options:

A.

risk taking and risk avoidance.

B.

known risk and unknown risk.

C.

identified risk and analyzed risk.

D.

varying degrees of risk.

Question 46

Which project risk listed in the table below is most likely to occur?

Options:

A.

1

B.

2

C.

3

D.

4

Question 47

Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?

Options:

A.

Feedback analysis

B.

Stakeholder analysis

C.

Communication management plan

D.

Stakeholder management plan

Question 48

Organizations perceive risks as:

Options:

A.

events that will inevitably impact project and organizational objectives.

B.

the effect of uncertainty on their project and organizational objectives.

C.

events which could have a negative impact on project and organizational objectives.

D.

the negative impact of undesired events on their project and organizational objectives.

Question 49

Which type of dependency is contractually required or inherent in the nature of the work?

Options:

A.

External

B.

Lead

C.

Discretionary

D.

Mandatory

Question 50

The risk shared between the buyer and seller is determined by the:

Options:

A.

assumption log.

B.

quality checklist.

C.

risk register.

D.

contract type.

Question 51

In which process group is the scope first defined?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Controlling

Question 52

The purpose of developing a project scope management plan is to:

Options:

A.

Manage the timely completion of the project.

B.

Ensure that the project includes all of the work required.

C.

Make sure the project will satisfy the needs for which it was begun.

D.

Reduce the risk of negative events in the project.

Question 53

Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?

Options:

A.

Teaming

B.

Collective bargaining

C.

Sharing

D.

Working

Question 54

What characteristic do project and operational work share in common?

Options:

A.

Performed by systems

B.

Constrained by limited resources

C.

Repetitiveness

D.

Uniqueness

Question 55

Monte Carlo is which type of risk analysis technique?

Options:

A.

Probability

B.

Quantitative

C.

Qualitative

D.

Sensitivity

Question 56

Plan Risk Management is the process of defining how to:

Options:

A.

Communicate identified risks to the project stakeholders.

B.

Conduct risk management activities for a project.

C.

Analyze the impact a specific risk may have on the project.

D.

Address unexpected risks that may occur during a project.

Question 57

At the end of the project, what will be the value of SV?

Options:

A.

Positive

B.

Zero

C.

Negative

D.

Greater than one

Question 58

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

Options:

A.

US$S000

B.

US$9500

C.

US$10,000

D.

US$12,500

Question 59

Lessons learned documentation is gathered during which of the following Project Management Process Groups?

Options:

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Question 60

Which tools or techniques are used during the Close Project or Phase process?

Options:

A.

Reserve analysis and expert judgment

B.

Facilitation techniques and meetings

C.

Expert judgment and analytical techniques

D.

Performance reviews and meetings

Question 61

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

Options:

A.

Interactive communication

B.

Claims administration

C.

Conflict management

D.

Performance reporting

Question 62

The process of identifying and documenting relationships among the project activities is known as:

Options:

A.

Control Schedule.

B.

Sequence Activities.

C.

Define Activities.

D.

Develop Schedule.

Question 63

Those who enter into a contractual agreement to provide services necessary for a project are:

Options:

A.

buyers

B.

sellers

C.

business partners

D.

product users

Question 64

Which of the following is a tool or technique of the Define Activities process?

Options:

A.

Rolling wave planning

B.

Precedence diagramming method (PDM)

C.

Alternatives analysis

D.

Parametric estimating

Question 65

Types of internal failure costs include:

Options:

A.

inspections.

B.

equipment and training.

C.

lost business.

D.

reworking and scrapping.

Question 66

Which is the correct formula for calculating expected activity cost for three-point estimating?

Options:

A.

Ce = (C0 + 6Cm + Cp)/4

B.

Ce = (6C0 + Cm + Cp)/4

C.

Ce = (C0 + 4Cm + Cp)/6

D.

Ce = (C0 + C„, + 4Cp) / 6

Question 67

When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

Options:

A.

Negative

B.

Zero

C.

Positive

D.

Free

Question 68

Which of the following is an output of Close Procurements?

Options:

A.

Accepted deliverables

B.

Organizational process assets updates

C.

Managing stakeholder expectations

D.

Performance reports

Question 69

Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

Options:

A.

Compromising

B.

Collaborating

C.

Smoothing

D.

Problem Solving

Question 70

A reward can only be effective if it is:

Options:

A.

Given immediately after the project is completed.

B.

Something that is tangible.

C.

Formally given during project performance appraisals.

D.

Satisfying a need valued by the individual.

Question 71

Which Knowledge Areas include processes from the Closing Process Group?

Options:

A.

Project Quality Management and Project Time Management

B.

Project Scope Management and Project Risk Management

C.

Project Stakeholder Management and Project Cost Management

D.

Project Integration Management and Project Procurement Management

Question 72

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

Options:

A.

Reserve analysis

B.

Three-point estimating

C.

Parametric estimating

D.

Analogous estimating

Question 73

Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

Options:

A.

Mandatory

B.

Discretionary

C.

Internal

D.

External

Question 74

A project manager builds consensus and overcomes obstacles by employing which communication technique?

Options:

A.

Listening

B.

Facilitation

C.

Meeting management

D.

Presentation

Question 75

In a weak matrix, the project managers role is:

Options:

A.

part-time

B.

full-time

C.

occasional

D.

unlimited

Question 76

Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?

Options:

A.

Crashing

B.

Fast tracking

C.

Leads and lags adjustment

D.

Parallel task development

Question 77

Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

Options:

A.

Smooth/accommodate

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Force/direct

Question 78

Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?

Options:

A.

Develop Project Management Plan

B.

Develop Project Charter

C.

Direct and Manage Project Execution

D.

Collect Requirements

Question 79

Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

Options:

A.

Coaching

B.

Avoidance

C.

Consensus

D.

Influencing

Question 80

Information collected on the status of project activities being performed to accomplish the project work is known as what?

Options:

A.

Project management information system

B.

Work performance information

C.

Work breakdown structure

D.

Variance analysis

Question 81

Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

Options:

A.

Force/direct

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Collaborate/problem solve

Question 82

Which of the following choices is a contract closure tool or technique?

Options:

A.

Contract plan

B.

Procurement plan

C.

Closure process

D.

Procurement audits

Question 83

Conflict should be best addressed in which manner?

Options:

A.

Early, in private, using a direct, collaborative approach

B.

Early, in public, using an indirect, collaborative approach

C.

Early, in private, using an indirect, cooperative approach

D.

As late as possible, in public, using a direct, confrontational approach

Question 84

The procurement process that documents agreements and related documentation for future reference is known as:

Options:

A.

Plan Procurements.

B.

Control Procurements.

C.

Close Procurements.

D.

Conduct Procurements.

Question 85

A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:

Options:

A.

Adaptive

B.

Predictive

C.

Incremental

D.

Iterative

Question 86

In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

Options:

A.

Start-to-start (SS)

B.

Start-to-finish (SF)

C.

Rnish-to-finish (FF)

D.

Finish-to-start (FS)

Question 87

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Question 88

Which tool and technique of quality planning involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?

Options:

A.

Histogram

B.

Quality audits

C.

Benchmarking

D.

Performance measurement analysis

Question 89

Which of the following inputs is required for the WBS creation?

Options:

A.

Project Quality Plan

B.

Project Schedule Network

C.

Project Management Software

D.

Project Scope Management Plan

Question 90

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?

Options:

A.

Communications management plan

B.

Human resource plan

C.

Quality management plan

D.

Procurement management plan

Question 91

The following is a network diagram for a project.

What is the critical path for the project?

Options:

A.

A-B-C-F-G-I

B.

A-B-C-F-H-I

C.

A-D-E-F-G-I

D.

A-D-E-F-H-I

Question 92

When should quality planning be performed?

Options:

A.

While developing the project charter

B.

In parallel with the other planning processes

C.

As part of a detailed risk analysis

D.

As a separate step from the other planning processes

Question 93

A contract management plan is a subsidiary of what other type of plan?

Options:

A.

Resource plan

B.

Project management plan

C.

Cost control plan

D.

Expected monetary value plan

Question 94

Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?

Options:

A.

Power/influence grid

B.

Power/interest grid

C.

Influence/impact grid

D.

Salience model

Question 95

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

Options:

A.

Timing

B.

Methodology

C.

Risk categories

D.

Budgeting

Question 96

The following is a network diagram for a project.

The total float for the project is how many days?

Options:

A.

5

B.

9

C.

12

D.

14

Question 97

Which is used to solicit proposals from prospective sellers?

Options:

A.

Procurement statement of work

B.

Resource calendars

C.

Procurement document

D.

Independent estimates

Question 98

What is the function of a Project Management Office (PMO)?

Options:

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client's overall business objectives.

B.

To coordinate and manage the procurement of projects relevant to the parent organization's business objectives and to administer the project charters accordingly.

C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.

D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.

Question 99

In the Define Activities process, the schedule management plan is used to:

Options:

A.

Capture the lessons learned from other projects for comparison.

B.

Contain the standard activity list.

C.

Document and support the project change requests.

D.

Prescribe the level of detail needed to manage the work.

Question 100

The milestone list is an input to which process from the Planning Process Group?

Options:

A.

Define Activities

B.

Estimate Activity Durations

C.

Estimate Activity Resources

D.

Sequence Activities

Question 101

An input to the Create WBS process is a:

Options:

A.

project charter.

B.

stakeholder register.

C.

project scope statement.

D.

requirements traceability matrix.

Question 102

Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?

Options:

A.

Facilitation techniques

B.

Expert judgment

C.

Analytical techniques

D.

Variance analysis

Question 103

A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?

Options:

A.

Identify Risks

B.

Control Risks

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Question 104

An output of the Create WBS process is:

Options:

A.

Scope baseline.

B.

Project scope statement.

C.

Organizational process assets.

D.

Requirements traceability matrix.

Question 105

Which of the following are placed at selected points in the work breakdown structure (WBS) for performance measurement?

Options:

A.

Control accounts

B.

Milestones

C.

Management points

D.

Measurement points

Question 106

Inputs to the Plan Risk Management process include the:

Options:

A.

cost management plan.

B.

risk management plan,

C.

activity list,

D.

risk register.

Question 107

The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

Options:

A.

Define Activities.

B.

Sequence Activities.

C.

Define Scope.

D.

Control Schedule.

Question 108

Which tool or technique is an examination of industry and specific vendor capabilities?

Options:

A.

Independent estimates

B.

Market research

C.

Analytical techniques

D.

Bidder conferences

Question 109

The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

Options:

A.

Work packages.

B.

Accepted deliverables.

C.

The WBS dictionary.

D.

The scope baseline.

Question 110

Portfolio Management is management of:

Options:

A.

a project by dividing the project into more manageable sub-projects.

B.

a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling.

C.

all projects undertaken by a company.

D.

a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.

Question 111

Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

Options:

A.

Expert judgment.

B.

Analytical techniques.

C.

Earned value management.

D.

Group decision-making techniques.

Question 112

In the basic communication model, which term refers to the method that is used to convey the message?

Options:

A.

Decode

B.

Encode

C.

Medium

D.

Noise

Question 113

The Process Group that involves coordinating people and resources, as well as integrating and performing the activities of the project in accordance with the project management plan is known as:

Options:

A.

Initiating.

B.

Planning.

C.

Executing.

D.

Monitoring and Controlling.

Question 114

Which of the following is a tool and technique used in all processes within Project Integration Management?

Options:

A.

Records management system

B.

Expert judgment

C.

Project management software

D.

Issue log

Question 115

An imposed date for completion of the project by the customer is an example of a project:

Options:

A.

deliverable

B.

assumption

C.

constraint

D.

exclusion

Question 116

Which stakeholder communicates with higher levels of management to gather organizational support and promote project benefits?

Options:

A.

Portfolio manager

B.

Project sponsor

C.

Project manager

D.

Project management office

Question 117

Which of the following is an input to the Direct and Manage Project Execution process?

Options:

A.

Approved change requests

B.

Approved contract documentation

C.

Work performance information

D.

Rejected change requests

Question 118

Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?

Options:

A.

Scope plan

B.

Product scope

C.

Scope management plan

D.

Scope baseline

Question 119

Which of the following will provide the basis for estimating, scheduling, executing, and monitoring and controlling project work?

Options:

A.

Activities

B.

Milestone list

C.

Work breakdown structure (WBS)

D.

Work packages

Question 120

Which of the following is an input into the Develop Project Team process?

Options:

A.

Enterprise environmental factors

B.

Organizational process assets

C.

Project staff assignments

D.

Performance reports

Question 121

Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:

Options:

A.

Conduct Procurements.

B.

Close Procurements.

C.

Administer Procurements,

D.

Plan Procurements.

Question 122

Which of the following methods of performance review examines project performance over time to determine if performance is improving or deteriorating?

Options:

A.

Earned value performance

B.

Trend analysis

C.

Cost-benefit analysis

D.

Variance analysis

Question 123

Which quality tool incorporates the upper and lower specification limits allowed within an agreement?

Options:

A.

Control chart

B.

Flowchart

C.

Checksheet

D.

Pareto diagram

Question 124

Who is responsible for reviewing change requests and approving or rejecting the change requests?

Options:

A.

Change control board

B.

Project manager

C.

Project management office

D.

Project sponsor

Question 125

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

Options:

A.

Acquire Project Team.

B.

Plan Human Resource Management.

C.

Manage Project Team.

D.

Develop Project Team.

Question 126

A project management office manages a number of aspects including the:

Options:

A.

Project scope, schedule, cost, and quality of the products of the work packages.

B.

Central coordination of communication management across projects.

C.

Assignment of project resources to best meet project objectives.

D.

Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.

Question 127

Which cost estimate technique includes contingencies to account for cost uncertainty?

Options:

A.

Vendor bid analysis

B.

Three-point estimates

C.

Parametric estimating

D.

Reserve analysis

Question 128

Which process should be conducted from the project inception through completion?

Options:

A.

Monitor and Control Project Work

B.

Perform Quality Control

C.

Perform Integrated Change Control

D.

Monitor and Control Risks

Question 129

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

Options:

A.

Slack

B.

Float

C.

Lag

D.

Lead

Question 130

Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?

Options:

A.

Cyclic

B.

Progressive

C.

Repetitive

D.

Iterative

Question 131

Which of the following is an input to Direct and Manage Project Execution?

Options:

A.

Requested changes

B.

Approved change requests

C.

Work performance information

D.

Implemented defect repair

Question 132

The project manager for XYZ stationers is sequencing the activities for the project to set up a new office. It is known from knowledge of best practices that it is better to wait for the painters to finish painting the walls before the new floors are installed. This is an example of which of the following types of dependency?

Options:

A.

Precedence

B.

Discretionary

C.

External

D.

Mandatory

Question 133

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

Options:

A.

Plan Human Resource Management.

B.

Acquire Project Team.

C.

Manage Project Team.

D.

Develop Project Team.

Question 134

Which characteristic is unique to project work and does not apply to operational work?

Options:

A.

Performed by individuals

B.

Limited by constraints

C.

Temporary

D.

Performed to achieve organizational objectives

Question 135

What provides information regarding the ways people, teams, and organizational units behave?

Options:

A.

Organizational chart

B.

Organizational theory

C.

Organizational structure

D.

Organizational behavior

Question 136

What is the tool and technique used to request seller responses?

Options:

A.

Procurement documents

B.

Expert judgment

C.

Bidder conferences

D.

Contract types

Question 137

To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:

Options:

A.

scope creep.

B.

a change request.

C.

work performance information.

D.

deliverables.

Demo: 137 questions
Total 918 questions