Which of the following is a group decision-making technique?
During project selection, which factor is most important?
Which is an output of the Collect Requirements process?
A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:
At the end of the project, what will be the value of SV?
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:
What are the identified risks for doing excessive decomposition in a WBS?
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
The three processes of Project Cost Management are:
Which of the following response strategies are appropriate for negative risks or threats?
Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?
A tool and technique used during the Define Scope process is:
What is project management?
Which type of dependency is contractually required or inherent in the nature of the work?
Expected monetary value (EMV) is computed by which equation?
Inputs to the Plan Risk Management process include the:
Which of the following is a tool or technique used in the Acquire Project Team process?
The process of identifying specific actions to be performed to produce project deliverables is:
Which of the following is a strategy to deal with positive risks or opportunities?
The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?
Activity cost estimates are quantitative assessments of the probable costs required to:
Resource calendars are included in the:
Which of the following change requests can bring expected future performance of the project work in line with the project management plan?
The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Which of the following are three inputs to the risk register?
The completion of the project scope is measured against the:
The process improvement plan details the steps for analyzing processes to identify activities which enhance their:
Plan-do-check-act is also known as:
The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:
At which stage of team development do members begin to work together, adjust work habits, and trust each other?
After Define Activities and Sequence Activities, the next process is:
An input of the Create WBS process is:
Which statement correctly describes the value of a business case?
The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?
Which process requires implementation of approved changes?
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
The probability and impact matrix is primarily used to:
Which technique is utilized in the Control Schedule process?
Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
Which of the following is an input to the Develop Project Charter process?
Which of the following is an output of Close Procurements?
Which of the following is a project constraint?
Which risk response strategy is common for both positive and negative risks?
Exhibit A is an example of which of the following types of Sequence Activities?

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:
The cost benefit analysis tool is used for creating:
Which input will be used when tasked with developing the human resource plan?
Which of the following is a tool and technique used to monitor risk?
Which quality control technique illustrates the 80/20 principle?
Funding limit reconciliation is a tool and technique used in which process?
How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
Which of the following are components of the technical project management skill?
What should a project manager use to determine how much money is needed to complete a project?
Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?
The features and functions that characterize a result, product, or service can refer to:
Stakeholder identification and engagement should begin during what phase of the project?
What is the difference between verified and accepted deliverables?
With regard to a project manager's sphere of influence in a project, which of the following does the project manager influence most directly?
A project manager called for a team meeting...................method did the team use
A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated. Which estimation method did the team use?
A project manager is identifying the risks of a project. Which technique should the project manager use?
To which knowledge area does the Collect Requirements process belong?
A project manager held a meeting and listed all team members' ideas for improving the product on a white board. What data gathering technique did the project manager apply?
What charts and (igures should project managers use during the Perform Quantitative Risk Analysis process?
Why is tailoring required in a project?
A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?
Project reporting is a tool that is most closely associated with which process?
During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?
What is one of the main purposes of the project chatter?
Which statement summarizes the role of the change control board?
A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.
Which strategies should the project manager take into account for risk management in this environment?
The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project Procurement Management processes?
Which is the order of steps in the Procurement Management process?
What process is included in Project Schedule Management?
When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process.
A project manager is formalizing acceptance of the completed project deliverables. What is an input to this process?
Which project manager competency is displayed through the knowledge, skills, and behaviors related to specific domains of project, program, and portfolio management?
What scenario describes when a project must be created due to market demand?
A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?
What important leadership quality/qualities should project managers possess?
In which sphere of influence is the project manager demonstrating the value of project management and advancing the efficacy of the project management office (PMO)?
Which are inputs for the Plan Quality Management process?
A firm contracted an event management company to conduct the annual sales day event. The agreement states that the event management company will charge the firm for the actuals and receive 8% of the total cost. What type of contract Is this?
A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because It is a foreign location.
Which type of life cycle would the project manager use in this case?
A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project manager's key responsibility during this phase?
A project team conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type of communication is this?
Which components of the project management plan are inputs used when creating the stakeholder engagement plan?
A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?
Which set of competencies should a project manager have?
Which of the following are outputs of the Define Scope process in Project Scope Management?
The primary purpose of the stakeholder register is to:
Which contract type is least desirable to a vendor?
Which of the following must be included in the risk register when the project manager completes the Identify Risks process?
What is the role of project management in terms of organizational strategy?
Which of the following tasks focuses on decomposing work packages?
What conflict resolution technique involves delaying the issue or letting others resolve it?
Which of the following is an example of facit knowledge?
What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization?
Which tools and techniques will a project manager use to develop a project charter?
Which of the following is used as an input to prepare a cost management plan?
Which set of activities should a project manager use as part of the Develop Team process?
In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?
The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project manager involved?
A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.
Which technique is the project manager using?
What tool or technique can improve a products final characteristics?
In which of the Risk Management processes is the project charter used as an input?
A new project manager wishes to recommend creating a project management office to senior management. Which statement would the project manager use to describe the Importance of creating the project management office?
A project stakeholder is requesting changes to the project plan. Which process group addresses this?
When can pre-assignment of project team members occur?
Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?
What is the name of a graphic display of project team members and their reporting relationships?
Which of the following statements correctly characterizes pull communication?
What is a hierarchically organized depiction of the identified project risks arranged by risk category?
Which tool is used to develop technical details within the project management plan?
What is the difference between the critical path and the critical chain?
Which technique is used in Perform Quantitative Risk Analysis?
Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
Change requests are an output from which Project Integration Management process?
When would resource leveling be applied to a schedule model?
Which of the following is TRUE about most project life cycles?
The integrative nature of project management requires which Process Group to interact with the other Process Groups?
Which defines the portion of work included in a contract for items being purchased or acquired?
The individual or group that provides resources and support for a project and is accountable for success is the:
Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?
A collection of projects managed as a group to achieve strategic objectives is referred to as a:
An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?
Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?
Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?
What name(s) is (are) associated with the Plan-Do-Check-Act cycle?
Which document includes the project scope, major deliverables, assumptions, and constraints?
The links between the processes in the Process Groups are often:
Which of the following is a tool and technique for Estimate Activity Durations?
The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?
Work performance information and cost forecasts are outputs of which Project Cost Management process?
Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?
Which of the following tools or techniques is used for Estimate Activity Durations?
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?
Taking out insurance in relation to risk management is called what?
To which process is work performance information an input?
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?
During which process group is the quality policy determined?
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?
Which Process Group typically consumes the bulk of a project's budget?
Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?
Cost baseline is an output of which of the following processes?
Projects are undertaken by an organization to support the:
When does Monitor and Control Risks occur?
Which activity is an input to the Conduct Procurements process?
Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?
Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?
Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?
Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?
Which organizational process assets update is performed during the Close Procurements process?
Which Develop Schedule tool and technique produces a theoretical early start date and late start date?
Which of the following is an input to Direct and Manage Project Execution?
What is one of the objectives of Project Risk Management?
The product scope description is used to:
What type of reward can hurt team cohesiveness?
Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?
Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?
Which is an example of Administer Procurements?
Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:
In which type of organizational structure are staff members grouped by specialty?
Which of the following is an output of Direct and Manage Project Execution?
Which type of chart is a graphic representation of a process showing the relationships among process steps?
Which of the following is an output of the Perform Integrated Change Control process?
Which process should be conducted from the project inception through completion?
Which of the following documents allows the project manager to assess risks that may require near term action?
A method to manage stakeholder expectations in the scope statement is to clearly:
Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?
A required input for Create WBS is a project:
Which of the following is a tool or technique of the Define Activities process?
Which of the following strategic considerations often results in project authorization?
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?
Which of the following is a tool and technique used in the Develop Schedule process?
The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:
Which is a communication method used in the Report Performance process?
What is the primary benefit of meeting quality requirements?
How is the schedule variance calculated using the earned value technique?
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
The definition of operations is a/an:
Another name for an Ishikawa diagram is:
Which of the following is an example of the simplest fixed-price contract?
The milestone list is an input to which process from the Planning Process Group?
The precedence diagramming method (PDM) is also known as:
In which process might a project manager use risk reassessment as a tool and technique?
Which is used to solicit proposals from prospective sellers?
Project contracts generally fall into which of the following three broad categories?
Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?
Which is an input to the Verify Scope process?
Which degree of authority does a project manager have on a project in a strong matrix organizational structure?
Which technique helps to determine the risks that have the most potential impact on a project?
The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:
Co-location is a tool and technique of:
Which of the following is an input to Develop Human Resource Plan?
During which process would stakeholders provide formal acceptance of the completed project scope?
What is the most accurate rough order of magnitude (ROM)?
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
Which process determines the risks that might affect the project?
An input to the Perform Quantitative Risk Analysis process is the:
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?
A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?
Which of the following is an output of the Distribute Information process?
Which of the following Project Communication Management processes uses performance reports as an input?
Which of the following correctly explains the term "progressive elaboration'?
Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?
Which standard has interrelationships to other project management disciplines such as program management and portfolio management?
Which tool or technique is used in Close Procurements?
The PV is $1000, EV is $2000, and AC is $1500. What is CPI?
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:
The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?
Quality metrics are an output of which process?
Which type of analysis is used as a general management technique within the Plan Procurements process?
Which of the following types of a dependency determination is used to define the sequence of activities?
A tool or technique in Perform Quality Control that a project manager would use is:
Which tool or technique is effective in a project in which the deliverable is not a service or result?
Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?
Which tool or technique is an examination of industry and specific vendor capabilities?
Which Control Quality tool is also known as an arrow diagram?
Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:
Which item is a formal proposal to modify any document, deliverable, or baseline?
The process of identifying and documenting relationships among the project activities is known as:
A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
The Monitoring and Controlling Process Group includes processes that:
Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?
The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:
The process of prioritizing risks for further analysis or action is known as:
A key benefit of the Manage Communications process is that it enables:
Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?
When should quality planning be performed?
Risk categorization is a tool or technique used in which process?
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?
A large portion of a projects budget is typically expended on the processes in which Process Group?
Stakeholder satisfaction should be managed as a key project:
Identify Risks is part of which Process Group?
A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:
Which cost is associated with nonconformance?
In which Knowledge Area is the project charter developed?
Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?
Which tool or technique is used in the Estimate Costs process?
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?
The Perform Integrated Change Control process occurs in which Process Group?
The basis of identification for current or potential problems to support later claims or new procurements is provided by:
Enterprise environmental factors are an input to which process?
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
When does the project team determine which dependencies are discretionary?
In the Plan Stakeholder Management process, expert judgment is used to:
Which Process Group and Knowledge Area include the Sequence Activities process?
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
Which item is an example of personnel assessment?
The Perform Quality Assurance process occurs in which Process Group?
Which input to the Plan Risk Management process provides information on high-level risks?
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:
An input to the Plan Cost Management process is:
A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?
An output of the Develop Project Team process is:
What are the Project Procurement Management processes?
Plan Schedule Management is a process in which Knowledge Area?
The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:
A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?
Which tool or technique is used in the Plan Scope Management process?
Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?
Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?
Which document describes the necessary information to determine if a project is worth the required investment?
Change requests are processed for review and disposition according to which process?
A Scrum team has a product backlog and a sprint backlog. Which of the following is a correct statement related to these artifacts?
Which of the following is used as input to prepare a cost management plan?
Which statement describes the Monitor Communications process?
Which characteristic defines the Delphi technique of group decision-making?
What process group establishes project scope: refines objectives, and defines the actions necessary to attain project objectives'?
What purpose does the hierarchical focus of stakeholder communications serve?
A project manager is creating a project charter to provide a direct link between the project and the organization's strategic objectives. What must be considered when creating this document?
What tool or technique is primarily used to plan risk responses'?
What estimating technique is used when there is limited information?
For a 10-day project, activity B ' s duration is three days, and activity C’s duration is two days What is the duration of activity A if activities B and C are performed in parallel?
Which subsidiary management plan.... during the project ilfe cycle?
Which Subsidiary management plan would a project manager create to manage Information dissemination during the project life cycle?
A Project manager is failing to secure critical equipment on time, and this resulting in delays in the manufacturing of the final product. Which knowledge area is the project manager handling?
The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will take?
Which tool should a project manager use to calculate cost variance for a project?
In a demonstration meeting with a customer, the project team presented deliverables that were considered ready for customer use. The team based the results on a checklist of all the required criteria for the project.
Which of the following elements is the team using?
Which of the in an adaptive project environment, which action helps the project manager?
Given the following information, what is the schedule variance (SV) for this project?
Early start date (ES): 16 weeks
Actual time: 12 weeks
Schedule performance index (SPI): 1.3
A project manager is seeking assistance from the business analyst for an IT project. What assistance can the business analyst provide?
What is an emerging practice in stakeholder engagement?
What is the primary benefit of the Manage Quality process?
Considering a highly dynamic project environment, which approach should the project manager adopt to manage the project team?
In the business analysis aspect of a construction project, what is the purpose of the requirements validation process?
A project team of telecommuters located in three different time zones regularly misses project deadlines Daily meetings often start and end with the same person talking and the rest of the team listening The project manager determines that communication among team members must be addressed.
What communication step is missing from the daily meetings?
Agile release planning provides a high-level summary timeline of the release schedule based on.
In an interactive communication model, how is the sender ensured that the message was understood by the receiver?
A key stakeholder has left the project management team. The team now has a new key stakeholder who is requesting project reports from team members out of sequence.
What should the project manager do first?
The handoff of the first version of a software application to the operational team has taken a month longer than anticipated. How could this extended transition time have been avoided?
What statement describes the function or responsibility of a project manager?
What can the cost management plan establish?
Which of the following set of items belongs to the communications management plan?
Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?
A team member, who is close to an influential stakeholder, has joined the project team. The stakeholder is routing requests for multiple reports through the new team member, and the team member reaches out to the project manager regarding this. What should the project manager do first?
What quantitative risk analysis technique is used to select the optimum course of action from a number of alternatives?
A project manager has joined the sponsor to verify the last deliverable of the project. The sponsor is measuring and examining the deliverable to determine whether it meets the requirements and product acceptance criteria. Which activity is being performed?
A team has been tasked with designing a product to address a problem they have never faced before. The project team is struggling to get traction as the solutions are not clear. What should the project manager do next?
Development of the benefits management plan occurs in which stage of the project life cycle?
A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure an effective requirements elicitation.
What should the business analyst do?
How can working in iterations increase the quality of the product being built?
A project manager is reviewing a few techniques that can be used to evaluate solution results. The intent is to uncover whether the solution responds properly to unintended cases.
Which evaluation technique should be used here?
Which set of tools and techniques is useful for estimating activity durations for the project schedule?
The project manager implemented the stakeholder engagement plan and realized that some uploads should be made. Which components of the project management plan should be modified?
Match each tool or technique with its corresponding Project Cost Management process.

A project manager is working on project cost management. The following information is current.
* Planned value = 30
* Actual cost = 35
* Earned value = 28
Considering this data, which project indicator is correct?
When presenting a product roadmap to an adaptive team, which form of communication is the most appropriate?
A project team member is estimating the cost of activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?
Which document can help a project manager to leverage historical project information?
Which can be used to convert a verified deliverable to an accepted deliverable?
An organization's project management office (PMO) has issued guidelines that require a specific template to be used for onboarding resources for a project. Where can the project manager find this template?
What are the project management processes associated with project quantity management?
A stakeholder is reading project documents given by the project manager. The stakeholder is
curious about the difference between a verified deliverable and an accepted deliverable.
Which of the following definitions can the project manager use to explain the difference?
The project manager needs to obtain proposals on costs of supplies purchased from an external source. In order to conduct this in a fair and unbiased way, what should the project manager conduct?
Which statement describes the relationship between Manage Quality process and Control process?
A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager.
What should the project manager do to address this issue?
A project manager is reviewing a past project with similar.... team choosing for tailoring?
A project manager is reviewing a past project with similar requirements to the project that is currently chartered. The project team decided to adopt quality tools, techniques and templates recommended at the organizational level after reviewing the lessons learned of the previous project What specific area of quality, is the project team choosing for tailoring?
The project manager needs to manage a critical issue immediately, and this requires action from the upper management of a specific stakeholder group. Which plan should plan the project manager consult?
Drag the five stages of team development on the left onto the blocks on the right to place them in sequential order.

The chart below is an example of a:

An input to the Control Quality process is:
When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:
The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:
In complex projects/ initiating processes should be completed:
In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?
A graphic display of project team members and their reporting relationships is known as a:
Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?
Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?
Variance and trend analysis is a tool and technique used in which process?
Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project's:
Project Stakeholder Management focuses on:
The following chart contains information about the tasks in a project.

Based on the chart, what is the cost variance (CV) for Task 6?
Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?
Which Manage Communications tool or technique focuses on identifying and managing barriers?
A disadvantage associated with virtual teams is that they:
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:
The component of the risk management plan that documents how risk activities will be recorded is called:
The primary benefit of the Plan Schedule Management process is that it:
An input to the Perform Integrated Change Control process is:
The following is a network diagram for a project.

The total float for the project is how many days?
The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:
Which element does a project charter contain?
Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?
Power, urgency, and legitimacy are attributes of which stakeholder classification model?
Which type of organizational structure is displayed in the diagram provided?

Those who enter into a contractual agreement to provide services necessary for a project are:
Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?
A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?
During which process does the project team receive bids and proposals?
Which quality tool may prove useful in understanding and estimating the cost of quality in a process?
Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?
A project manager who communicates to the project team though email is using which type of communication?
The following chart contains information about the tasks in a project.

Based on the chart, what is the schedulevariance (SV) for Task 8?
At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?
Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?
Success is measured by benefits realization for a:
Which document in the project management plan can be updated in the Plan Procurement Management process?
The following is a network diagram for a project.

How many possible paths are identified for this project?
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
Every project creates a unique product, service, or result that may be:
Which project risk listed in the table below is most likely to occur?

Completion of the product scope is measured against the product:
The purpose of the Project Communications Management Knowledge Area is to:
While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:
The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:
Which item is a cost of conformance?
The degree, amount, or volume of risk that an organization or individual will withstand is called risk:
When the business objectives of an organization change, project goals need to be:
Requirements documentation will typically contain at least:
Which tools or techniques are used during the Close Project or Phase process?
The process of obtaining seller responses, selecting a seller, and awarding a contract is called:
The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:
The process of defining how the project scope will be validated and controlled is known as:
Project deliverables that have been completed and checked for correctness through the Control Quality process are known as: