What is the purpose of a Project Target Agreement (PTA)?
In which situation is it required to update/change the cost baseline?
Which of the following cost components are allocated to a non-site level WBS element?
Which of the following is NOT an example of cost of poor quality?
The estimated value of the work actually accomplished is:
When should lessons learned be performed?
When should a risk be avoided?
During the post cost calculation, the review of the subcontracting costs:
Your project is ongoing, all partner contracts have been renegotiated and new prices (higher by 8%) came into effect immediately. If all the other circumstances in your project remain unchanged, your PCA [%] value will:
What costs are included in NCC reporting based on current guidelines?
Company A is working on a project. The project‘s budget is €10,000. The planned value as of date X is €4,000. The project is 30% completed. 60% of the budget has been spent to date X. The actual cost (AC) to date for the project is:
Which of the following is NOT part of the IPM suite?
In relation to the program life cycle, when is the correct time to freeze the project scope?
Which of the following is NOT a contract type:
Why is the project resource plan required during the 'Create Customer Solution' phase?
Under what circumstances should the costs associated with the execution of the quality management plan be included in the project cost baseline?
Project "A" has experienced difficulties in the deliveries of one of its key suppliers. It has been estimated by the project team that, if the supplier is one week late for the next scheduled delivery, it will cost €10,000. The probability of the supplier being late is 50 %, based on the fact that this has happened before on the project. It is decided not to take any risk mitigation actions. What is the TERC for this risk?
During project setup, an identified risk event with a 100% probability of occurrence is:
During which stage of risk planning are risks prioritized based on probability and impact?
The foundation for successful claim management is:
What are key components of EVM methodology?
The project manager is only authorized to place orders to vendors:
Which of the following inputs are part of the sales to delivery handover?
At a given point in time, a project has CV = €700, CPI = 0.7, SV = €-1,300 and SPI = 1.3. the project is:
What transactions still can be done after the project financial closure?
Company A is working on a project. The project‘s budget is €10,000. The Planned value as of date X is €4,000. The project is 30% completed. 60% of the budget has been spent. If the company continues to spend money at the same rate, what will the project cost (EAC)?
Which accounting indicator can have any of the CR categories linked?
What is the recommended frequency for approving working time in WTR?
What will be the resulting performance index if the actual cost is higher than the earned value?
When a Customer Contract is not yet signed and a purchase order has not yet been received, in which circumstances can a service be subcontracted?
To which of the following tools is SAP P20 linked?