What is a Sprint?
When is a Sprint complete?
A team has eleven members spread over two locations across two time zones. One of the locations has six team members and the other team has five.
Where should a Scrum Master be located?
A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis.
What is the elapsed time required to complete the story?
Sprint planning should result in a commitment on what will be delivered at the end of the Sprint. Who makes this commitment?
In a Scrum project, when would a requirement get added to the Product backlog?
Why are estimates expressed in terms of story points difficult to explain outside of the team?
An engineering organization is transforming their project management method to use Agile Scrum.
What is the best approach to the transformation?