A principle states 80% of the issues are the result of 20% of the causes. Which of the following types of diagrams is based on this principle?
For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?
Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?
Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?
During the execution phase, user accepted testing failed; nonetheless, the vendor PM is insisting that the program manager approve the invoice for this phase. Which of the following actions should the Program manager take?
Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?
During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?
A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?
A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?
During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?
A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?
During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?
During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?
Which of the following statements best describes zero-based budgeting?
A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?
During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:
Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?
A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?
A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?
A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?
A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?
Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?
An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?
During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?
Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?
Given the following information:
Which of the following represents the critical path of the project?
A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California. Which of the following is most important for the project manager to consider when setting up the session?
An software engineer is applying new updates to a program in a sandbox environment. Which of the following risk strategies best describes this practice?
After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?
Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).
Which of the following should a project manager consult when deciding how to send updates regarding deliverables?
Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?
A project manager is coordinating multiple teams of six people that will each provide feedback for a new product. The teams are recording their opinions, which may be used to define the final product that is sent to mass production. Which of the following best describes this technique?
A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?
Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?
A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?
A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?
Which of the following is a capital expense?
A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?
A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).
During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?
After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?
Which of the following communication tools would a project manager use to broadcast information without being assured the information will be received?
In the initiation phase, a PM is reviewing the objectives, the high-level requirements, the success criteria, and the budget resources. Which of the following action items will benefit from this analysis?
A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?
Which of the following is required to provide a hardware installation with a Tier 5 redundancy level?
A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?
A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)
A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?
Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?
A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?
Which of the following tools is best to use when conducting project meetings across time zones?
Which of the following tools is best to use for storing lessons learned?
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?
A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:
• Purpose
• Scope of work
• Location of work
• Period of performance
• Deliverables schedule
• Applicable standards
• Acceptance criteria
• Special requirements
• Payment schedule
Which of the following documents did the client provide to the project manager?
Which of the following cloud models can be used to speed up the development of a service that integrates with the operating system and accelerates the delivery of a software project?
A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?
A project manager has received different functional requests from three individual stakeholders. The project manager is able to have all parties concede somewhat in order to find a reasonable solution. Which of the following outcomes would most likely occur?
Which of the following would be the most helpful in providing customers with an application accessible via a web browser?
Which of the following should be considered first when determining the privacy management for project data?
Which of the following is a consideration when determining a project's ESG factors?
During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?
A project manager is assigned an initiative in a highly regulated industry that requires employees to safeguard certain pieces of PII. Which of the following is the best approach for the project manager to keep the information confidential?
Which of the following activities would a project manager perform during the closing phase? (Select THREE).
A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:
Based on the chart, which of the following is the current status of the project?
A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?
A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?
A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?
Which of the following software programs would be BEST to use lo store information related to business transactions?
Which of the following items must be protected as Pll? (Select TWO).
A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.
Which of the following dependencies is most likely happening?
When assigning access, classifying information based on sensitivity is referred to as:
A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?
A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:
• Two developers
• High uncertainty about existing systems
• Risk of frequent requirement changes
• Tight deadlines
Which of the following project methodologies would be best to use in this situation?
A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?
A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?
During a brainstorming session, a project team is elaborating on what caused the unexpected crash of the website that the team was developing. Given the following:
Which of the following was the initial cause of the issue?
Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?
A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?
An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the most important prerequisites? (Select two).
Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?
A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?
Which of the following activities are performed during the closing phase? (Select three).
In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?
A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?
A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?