The project has an AC of $5,000. Which of the following would be used to determine the budget needed to complete the project?
The project manager has outsourced a call center to a company in another region. The project manager receives reports that customers sometimes cannot hear the instructions given by call center employees. Which of the following is the MOST likely cause of the reports?
A project manager is performing activity sequencing. The project manager is only using start to finish dependencies. Dummy activities are being utilized to define all logical relationships. Which of the following methods is the project manager demonstrating?
A key stakeholder has asked the project manager to complete the project a week earlier than expected. To accomplish this objective, the project manager will have to ask the project team to work overtime, which will increase the cost of the project. Which of the following should be the NEXT step?
A project manager is performing activity sequencing with the project team. Each activity is written in a box with arrows linking the boxes according to their dependencies. Which of the following tools is the project manager utilizing?
A company manager has turned in project objectives, and requests that the project manager start the project immediately. The project manager informs the company manager that the project cannot be started. Which of the following is an appropriate reason for not starting the project?
A project manager is receiving many requests for changes to a project. Which of the following did the project manager fail to complete?
Which of the following is the BEST way to manage stakeholder expectations?
Two employees do not want to work with each other. The project manager tells the employees to perform the tasks or find other employment. Which of the following conflict resolution styles is being used?
In order to complete the pre-project setup, which of the following is the MOST important task of the project sponsor?
Communication preferences, cultural differences, and language barriers are BEST described as which of the following?
Which of the following activities are associated with a project kick-off meeting? (Select Two).
The project sponsor has just requested a status report be emailed to all project stakeholders every two weeks. Which of the following documents needs to be updated?
Which of the following would require that the project risk register be updated?
In working with the risk management plan all of the following are ways of dealing with opportunities EXCEPT:
Monitoring and controlling project work is a control process function that spans from:
A stakeholder asks the project manager to finish a project early. The project manager should ask the stakeholder to FIRST:
A project manager has decided to reduce the impact of a possible threat. Which of the following risk response strategies BEST describes this action?
When would a project manager have a closure meeting? (Select Three).
Which of the following is the correct formula for computing a projects SPI?
In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the EV of this project?
Two team members refuse to work together and have undermined the project with their constant bickering. The project manager needs both of them to complete the project. The team members meet and agree to work at different times. Which of the following conflict resolution styles is being used?
Which of the following processes incorporates the make-or-buy analysis?
A project manager seeks to implement a change control system. Which of the following elements are essential for this system to be effective? (Select Three).
Quality assurance is performed during which phase of a project?
Which of the following is MOST likely to be included in a communication plan?
Which of the following is an important aspect of formal project closure?
Which of the following is a component of a project charter?
Which of the following tools is the BEST to determine the cause of a problem?
Which of the following resource leveling techniques describes schedule compression by performing activities concurrently?
Which of the following is a representation of the amount of money spent on project work at a point in time?
Which of the following is the correct progression of the project life cycle?
An ongoing project requires several parts manufactured at an outside vendor. If the vendor has sufficient quantity and can still ship today, the parts should be received in five days; although in most cases an order of this size requires ten days. Allowing for an upcoming holiday and some potential bad weather the shipment could take up to twenty-one days. Using the PERT method, which of the following is the correct time estimate for a parts delivery?
Which of the following is used in quality control?
Which of the following is a quantitative risk analysis tool or technique?
Which of the following is a characteristic of a project charter?
A Pareto diagram focuses attention on which of the following?
The change control board has requested that a project manager evaluate the impact of a major change request that will affect the timetable of several work-packages. Which of the following actions should the project manager undertake FIRST?
Which of the following is the FINAL step in the pre-project setup phase?
Which of the following is the method for determining the critical path of a project?
Various technologies exist to complete a project, but the project manager is not well versed in these technologies. Which of the following can the project manager initiate to assist with the decision?
Pareto charts helps the project manager with which of the following?
A team member on a project uncovers a minor risk with the quality of a purchased component. The team uses their combined expert judgment to determine that the risk to the deliverable is very low. Which of the following is the MOST likely action the project manager should take?
Which of the following is found in project closure documentation?
Crashing a schedule involves which of the following?
Which of the following describes the point in time when resources can be assigned to scheduled tasks?
Given the following information: Pessimistic estimate is 30 days Most Likely estimate is 15 days Optimistic estimate is 10 days Which of the following is the expected duration for this scheduled activity?
A stakeholder has determined the need to update their payroll method with a new system. Which of the following is the FIRST activity the corporation should perform?
A project manager is informed that material expenditures will increase. Which of the following documents should be referenced to address this increase?
A project can be defined as which of the following?
A product has been sent to an outside vendor for testing. During their testing it was determined that the product is not meeting the quality standards. The project manager scheduled a meeting to review their findings. Which of the following BEST describes this situation?
Which of the following is included in the project scope document? (Select Two).
Which of the following are created using information contained in the work breakdown structure (WBS)? (Select Two).
A project manager is performing activity sequencing using the arrow diagramming method (ADM). Which of the following is true of ADM?
Which of the following represents the appropriate order of an effective change management process?
Which of the following techniques can a project manager use to assist with quality planning? (Select Three).
A project manager is reviewing the ownership, date, and the necessary training for a deliverable. Which of the following documents would include this information?
A project budget has been reduced by 10 percent, but the project has a critical deadline. Which of the following should the project manager do FIRST to complete the project on time?
Two members of a team have had difficulty working together in the past. Which of the following should the project manager do to facilitate communication between the team members?
Which of the following quality control tools illustrates the various factors that may be linked to potential problems or effects?