As a tester, as part of a V-model project, you are currently executing some tests aimed at verifying if a mobile app asks the user to grant the proper access permissions during the installation process and after the installation process. The requirements specification states that in both cases the app shall ask the user to grant access permissions only to the camera and photos stored on the device. However, you observe that the app also asks the user to grant access permission to all contacts on the device. Consider the following items:
[I]. Test environment
[ii]. Expected result
[iii]. Actual result.
[IV] Test level.
[V]. Root cause.
Based on only the given information, which of the items listed above, are you able to CORRECTLY specify in a defect report?
Which of the following statements about error guessing is true?
Consider an estimation session in which a six-member Agile team (Memb1..... Memb6) uses the planning poker technique to estimate a user story (in story points). The team members will use a set of cards with the following values: 1,2, 3,5, 8,13,21. Below is the outcome of the first round of estimation for this session:
Which of the following answers BEST describes how the estimation session should proceed?
The whole-team approach:
Which of the following is an advantage of the whole team approach?
For each test case to be executed, the following table specifies its dependencies and the required configuration of the test environment for running such test case:
Assume that C0NF1 is the initial configuration of the test environment Based on this assumption, which of the following is a test execution schedule that is compatible with the specified dependencies and allows minimising the number of switches between the different configurations of the test environment^
Scenario 2 “Big Drop”:
A company“The Big Drop”providesbulk discounts and frequent customer discountsas follows:
How manypossible decision rulescan be extracted from this table?
A system has a self-diagnostics module that starts executing after the system is reset. The diagnostics are running 12 different tests on the systems memory hardware. The following is one of the requirements set for the diagnostics module:
'The time taking the diagnostics tests to execute shall be less than 2 seconds' Which of the following is a failure related to the specified requirement?
Which of the following statements about checklist-based testing is TRUE?
The following rules determine the annual bonus to be paid to a salesman of a company based on the total annual amount of the sales made (referred to as TAS).
If the TAS is between 50k€ and 80k€, the bonus is 10%. If the TAS exceeds 80k€ by a value not greater than 40k€, the bonus is 15%. Finally, if the TAS
exceeds the maximum threshold which entitles to a 15% bonus, the bonus is 22%.
Consider applying equivalence partitioning to the TAS (Note: 1k€ = 1000 euros).
Which one of the following answers contain only test cases that belong to the same equivalence partition?
The four test levels used in ISTQB syllabus are:
1. Component (unit) testing
2. Integration testing
3. System testing
4. Acceptance testing
An organization wants to do away with integration testing but otherwise follow V-model. Which of the following statements is correct?
As a result of the joint evaluation of a product version with the customer, it has been concluded that it would be appropriate to retrieve an earlier version of the product and carry out a benchmark. Depending on the result, further development will be carried out based on the current version or the retrieved version.
Which mechanism, process, and/or technique will allow the specific version (including the testing work products) of a given software product to be restored?
A requirement specifies that a certain identifier (ID) must be between 5 and 10 characters long, must contain only alphanumenc characters, and its first character must be a letter As a tester, you want to apply one-dimensional equivalence partitioning to test this ID. This means that you have to apply equivalence partitioning individually: to the length of the ID, the type of characters contained within the ID, and the type of the first character of the ID. What is the number of partitions to cover?
Which of the following statements about white-box test techniques is true?
Which of the following is not an example of a typical generic skill required for testing?
Which of the following applications will be the MOST suitable for testing by Use Cases
Use Scenario 1 “Happy Tomatoes” (from the previous question).
Using theBoundary Value Analysis (BVA)technique (in its two-point variant), identify the set of input values that provides the HIGHEST coverage.
Test automation allows you to:
Which two of the following statements describe the advantages provided by good traceability between the test basis and test work products?
I. Analyzing the impact of changes.
ii. A measure of code quality.
iii. Accurate test estimation.
iv. Making testing auditable.
Select the correct answer:
An application is subjected to a constant load for an extended period of time as part of a performance test While running this test, the response time of the application steadily slows down, which results in a requirement not being met This slowdown is caused by a memory leak where the application code does not properly release some of the dynamically allocated memory when it is no longer needed. Which of the following statements is TRUE?
Which of the following statements about the shift-left approach is FALSE?
Which ONE of the following options BEST describes thethird test quadrant (Q3)?
Consider the followingiteration planning taskswhere a tester can provide value:
Break down user stories into tasks (particularly testing tasks)
Estimate test effort for all testing tasks
Identify and refine functional and non-functional aspects of the test object
Which ONE of the following tasks should be ADDED to the above list?
Scenario 1 “Happy Tomatoes” (used for questions 20-22):
An intelligent application for agricultural use incorporates temperature sensors located at different points of an enclosure. The sensors measure and record the temperature at regular intervals and extract the statistical values for these measurements. These values include the average daily temperature.
A new variety of tomatoes is currently being grown and the“World Organization for Happy Tomatoes”has established temperature ranges related to vegetative development.
When the system establishes that the average temperature is within a specific range, it emits a value that will be used to monitor and control the crop.
Using theequivalence partitioningtechnique, identify the set of input values that provides the HIGHEST coverage.
Consider a review for a high-level architectural document written by a software architect. The architect does most of the review preparation work, including distributing the document to reviewers before the review meeting. However, reviewers are not required to analyze the document in advance, and during the review meeting the software architect explains the document step by step. The only goal of this review is to establish a common understanding of the software architecture that will be used in a software development project.
Which of the following review types does this review refer to?
Consider the following list of activities (I to V):
I. Test design
II. Test planning
III. Review test basis
IV. Be a facilitator of a peer review
V. Test monitoring and control
Which ONE of the following options identifies the activities that the test management role is MAINLY focused on?
Which of the following statements best describes how configuration management supports testing?
A test status report SHOULD:
Consider the following user story about an e-commerce website's registration feature that only allows registered users to make purchases ; As a new user, I want to register to the website, so that I can start shopping online"
The following are some of the acceptance criteria defined for the user story
[a] The registration form consists of the following fields: username, email address, first name, last name, date of birth, password and repeat password.
[b] To submit the registration request, the new user must fill in all the fields of the registration form with valid values and must agree to the terms and conditions.
[c] To be valid, the email address must not be provided by free online mail services that allow to create disposable email addresses. A dedicated error message must be presented to inform the new user when an invalid address is entered.
[d] To be valid, the first name and last name must contain only alphabetic characters and must be between 2 and 80 characters long A dedicated error message must be presented to inform the new user when an invalid first name and/or the last name is entered
[e] After submitting the registration request, the new user must receive an e-mail containing the confirmation link to the e-mail address specified in the registration form
Based only on the given information, which of the following ATDD tests is MOST LIKELY to be written first?
A typical objective of testing is to ensure that:
Metrics can be collected during and at the end of testing activities to assess which of the following?
i. Progress against the planned schedule and budget.
II. Current quality of the test object.
Hi. Adequacy of the test approach.
iv. Effectiveness of the test activities with respect to the objectives.
v. All the above.
Select the correct answer:
Which ONE of the following statements would you expect to be the MOST DIRECT advantage of the whole-team approach?
Which of the following is a factor that contributes to a successful review?
For each of the test cases to be executed, the following table specifies the priority order and dependencies on other test cases
Which of the following test execution schedules is compatible with the logical dependencies and allows executing the test cases in priority order?
Atypical generic skill required for the role of tester is the ability to
The statement: "Test activities should start in the early stages of the lifecycle, adhering to the testing principle of early testing” is relevant to which of the recognized software development models?
In which one of the following test techniques are test cases derived from the analysis of the software architecture?
You are testing a system that is used in motor vehicles to warn the driver of an obstacle when re-versing. Output is provided by a series of LED lights (green, yellow, and red), each illuminated based on clearly defined conditions.
The following summary describes the functionality:
•Object within 10 metres, green LED lit.
•Object within 5 metres, yellow LED lit.
•Object within 1 metre, red LED lit.
•Setting sensitivity mode to "ON" will result in only the red LED being lit when the object is within 1 metre.
The following decision table describes the rules associated with the functioning of this proximity warning system:
Which intended functionality is tested by Rule 5 in the decision table?
Which of the following statements about the shift-left approach is true?
Use Scenario 1 “Happy Tomatoes” (from the previous question).
When running test caseTC_59, the actual result fort = 35degrees Celsius isOUTPUT = Xinstead of the expected output.
Which information should NOT be included in the defect report?
Which of the following statements about the test pyramid is TRUE?
Mark the correct sentences:
* Defects are a result of environmental conditions and are also referred to as "Failures"
* A human mistake may produce a defect
* A system mil totally fail to operate correctly when a failure exists in it
* When a defect exists in a system it may result in a failure
* Defects occur only as a result of technology changes
Which of the following statements refers to good testing practice to be applied regardless of the chosen software development model?
Which ONE of the following options MOST ACCURATELY describesbranch testing?
The acceptance criteria associated with a user story:
Which ONE of the following options BEST describes black-box test techniques?
Which of the following statements about static testing and dynamic testing is true?
Which ONE of the following statements about maintenance testing is CORRECT?
Which of the following best describes the relationship between a test progress report and a test summary report?
Which of the following is not an example of a typical content of a test completion report for a test project?
The following diagram displays the logical dependencies between requirements and the individual requirement priorities. For example, "R2->R3" means that R3 is dependent on R2. Priority is indicated by the number next to the letter ”P" i.e. P1 has a higher priority than P2.
Which one of the following options best describes the test execution sequence using both requirement dependency and priority
Which of the following statements about retrospectives is TRUE?
Which of the following is a typical potential risk of using test automation tools?
Which of the following statements is true?
Which of the following lists factors That contribute to PROJECT risks?