Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The requirement to 'install a heat reclamation system' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.
Is this an appropriate action related to acceptance criteria?
The Timebox to deliver the online reservation system through the Hoy Hall website has experienced a major issue. During Timebox C a test was completed to
simulate an attack on the financial element of the online reservation system, with the intention of finding security weaknesses. It was found that it was
potentially possible to gain access to the system, its functionality and data. Further work is therefore needed to meet the information security elements of a
customer financial transaction.
Answer the following question about the actions to be taken by each role.
Column 1 describes a list of actions related to dealing with the security issue with the hotel reservation system. Column 2 lists the key roles. For each action in Column 1,
select from Column 2 the role that should carry out the action.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1
Advise how the legislation on the transfer of data will affect the requirements
and the system.
Agree the changes needed to the corporate technical architecture with the
Architecture Angels IT support team.
Ensure the information security vulnerability is communicated to the AA Head
Office IT Director.
Evaluate the impact of proposed security controls on the business and decide
on the most suitable solution.
Reprioritise the requirements on the Prioritised Requirements List associated
with the security issue.
Column 2
Project Manager
Business Sponsor
Business Visionary
Technical Coordinator
Business Analyst
Team Leader
Business Ambassador
Solution Developer
During Timebox A, the Local Planning Authority Officer was sometimes asked to attend the Daily Stand-up meeting as a temporary Specialist team member, to represent
any Planning Authority issues.
Is this an appropriate application of Agile Project Management for this project?
How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?
Find out who is responsible for challenging the priority of requirements and deal with them accordingly.
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility.
Remember to limit your answers to the number of selections requested in each question.
Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?
There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as
it evolves.
Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2
can be used once, more than once or not at all.
Column 1
1) In order to get an objective
view, the financial transaction
function is to be tested by
someone from Finance who
has had no involvement in its
development.
2) Before the developer works on
the printing function for the
policy documents, the Sales
Manager will review a prototype
of the online application form
for the new coffee shop
insurance product with the
solution tester.
3) Security test scripts have been
provided by the company's
bank. These scripts will be used
to test the link from the
company's website to the
banking system, which is to be
developed specifically to achieve these tests
4.
The addition of the new coffee
shop insurance product may
threaten the stability of the
existing website. As a primary
route to market this is
unacceptable. The website's
capacity to run additional pages
is to be verified before any
other tests are performed.
5.
The Must Have and Should
Have requirements are to be
tested before the Could Have
requirements.
Column 2
Collaborative Testing
Repeatable Testing
Independent Testing
Prioritised Testing
Test-Driven Development
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each
question.
Which 2 statements describe the appropriate application of Agile Project
Management when developing the Feasibility Assessment?
Each of the following questions includes a list of true statements about individuals from Architecture Angels and Timber Tigers who have been appointed to the
project team. Only 2 statements explain why, in the context of an Agile team, the individual is a suitable candidate for that role.
Remember to limit your answers to the number of selections requested in each question.
Which 2 statements explain why the Architecture Angels' Finance Director would be an appropriate Business Sponsor?
How should the Project Manager assist the plumbers to deliver the plumbing?
Using the Project Scenario, answer the following question about the activities in the Agile project lifecycle.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.
Assertion:-
1. The rooms and facilities must be deployed into live use at the end of each Timebox.
BECAUSE
Reason:
Evolutionary Development and Deployment must be combined in a Timebox where the integration of several teams is required.
2. The tasks associated with each Solution Development Timebox should be included
in the Delivery Plan.
BECAUSE
Reason:
A typical Delivery Plan will provide a schedule of Timeboxes and any other high level activities for the imminent Project Increment.
3. The development approach should have been agreed during Foundations.
BECAUSE
Reason:
The Development Approach Definition must be created before Evolutionary
Development can commence.
4. The resources from Timber Tigers and Earth Excavations should have been engaged
before the start of Evolutionary Development.
BECAUSE
Reason:
Commitment to delivery is based on pre-agreed resource levels at the project level.
5. A final Deployment phase should be held after Timebox C has completed.
BECAUSE
Reason:
The Deployed Solution is assessed post-project to confirm whether the expected benefits have been
achieved.
Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox
Plan for Timebox B?
Which 2 statements represent appropriate entries for the Development
Approach Definition?
Several of the web developers working on the project have no Agile
experience. When answering the questions in the Project Approach
Questionnaire (PAQ), the Project Manager could not agree with the statement
'all members of the project understand and accept the DSDM approach'.
What action should the Project Manager take?
Xan Insurance Company is a friendly company with no separate private offices
for individual managers. Staff members prefer to wander around the office
space and have one-to-one chats rather than use email or have lots of
meetings.
What action should the Project Manager take when planning for effective
communication throughout the Web project?
Answer the following questions about the DSDM Lifecycle.
Decide if each observation is an appropriate application of Agile Project Management for
this project and select the option that supports your decision.
When the project was in the Feasibility phase it was initially proposed by the Finance
Manager that it was a fixed price for a fixed specification' project. The Project Manager
has decided that the best way to tackle it would be to leave the development of the least
valuable features of the product until last.
Is this an appropriate application of the DSDM lifecycle?
Xan Insurance Company operates from one location - a large, open-plan
office in the centre of a city. Those employees that will be working within the
Solution Development Team are all based in this office but work at different
ends of the office in separate departments.
What action should the Project Manager suggest to ensure the most effective
collaboration of the Solution Development Team?
The Solution Development Team are progressing through the first Structured
Timebox.
What should the Project Manager do to lead the team at this time?
Answer the following questions about the contents of the DSDM
products.
Each of the following questions includes true statements about the project
but only two statements are appropriate entries for the DSDM product
identified.
Remember to limit your answers to the number of selections requested in
each question.
Which 2 statements represent appropriate entries for the Business Case?
The Solution Development Team are progressing through the first Structured
Timebox.
What should the Project Manager do to lead the team at this time?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following question
about assigning the Agile Project Management team roles within this
project.
Lines 1 to 5 in the table below consist of an assertion statement and a
reason statement. For each line identify the appropriate option, from options
A to E. that applies. Each option can be used once, more than once or not
at all.
Which 2 statements represent appropriate entries for the plan for Post-Project
activities?
A difference of opinion on the outcome of an earlier project has created a
'them and us' culture between the Sales Department and the Operations
Department.
What action should the Project Manager take to resolve this?