New Year Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

APMG-International AgilePM-Practitioner Agile Project Management (AgilePM) Practitioner Exam Exam Practice Test

Agile Project Management (AgilePM) Practitioner Exam Questions and Answers

Question 1

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

The requirement to 'install a heat reclamation system' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.

Is this an appropriate action related to acceptance criteria?

Options:

A.

Yes, because only Must Have requirements should be fully understood.

B.

Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox.

C.

No, because it is necessary to understand the full detail of all the work for completion in the Solution Development Timebox during Investigation.

D.

No, because it indicates that the Solution Development Team has NO intention of delivering the Should Have requirements.

Question 2

The Timebox to deliver the online reservation system through the Hoy Hall website has experienced a major issue. During Timebox C a test was completed to

simulate an attack on the financial element of the online reservation system, with the intention of finding security weaknesses. It was found that it was

potentially possible to gain access to the system, its functionality and data. Further work is therefore needed to meet the information security elements of a

customer financial transaction.

Answer the following question about the actions to be taken by each role.

Column 1 describes a list of actions related to dealing with the security issue with the hotel reservation system. Column 2 lists the key roles. For each action in Column 1,

select from Column 2 the role that should carry out the action.

Each selection from Column 2 can be used once, more than once or not at all.

Column 1

    Advise how the legislation on the transfer of data will affect the requirements

and the system.

    Agree the changes needed to the corporate technical architecture with the

Architecture Angels IT support team.

    Ensure the information security vulnerability is communicated to the AA Head

Office IT Director.

    Evaluate the impact of proposed security controls on the business and decide

on the most suitable solution.

    Reprioritise the requirements on the Prioritised Requirements List associated

with the security issue.

Column 2

    Project Manager

    Business Sponsor

    Business Visionary

    Technical Coordinator

    Business Analyst

    Team Leader

    Business Ambassador

    Solution Developer

Options:

Question 3

During Timebox A, the Local Planning Authority Officer was sometimes asked to attend the Daily Stand-up meeting as a temporary Specialist team member, to represent

any Planning Authority issues.

Is this an appropriate application of Agile Project Management for this project?

Options:

A.

Yes, because all stakeholders should attend the Daily Stand-up meetings.

B.

Yes, because each team member will have an opportunity to highlight any Planning Authority issues that may otherwise hinder their progress.

C.

No, because NOT all members of the Solution Development Team will attend the Daily Stand-up.

D.

No, because only members of the Solution Development Team should be permitted to attend Daily Stand-up meetings.

Question 4

How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?

Options:

A.

The Solution Development Team should revise the Timebox Plans for Timeboxes B and C.

B.

The Solution Development Team should commence understanding and delivering the new requirement.

C.

The Architect, in the role of Technical Co-ordinator, should escalate the issue to Architecture Angels' Senior Management Team.

D.

The Project Manager should escalate the issue to the Marketing Director, who is in the role of Business Visionary.

Question 5

Find out who is responsible for challenging the priority of requirements and deal with them accordingly.

Options:

A.

Ask the Team Leader to resolve the situation.

B.

Ask the Marketing Director to explain to the Solution Development Team why the windows are a Must Have priority.

C.

Remove empowerment from the Solution Development Team.

D.

What action should the Project Manager take when dealing with the Solution Development Team's argument that the windows should not be a Must Have priority?

Question 6

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility.

Remember to limit your answers to the number of selections requested in each question.

Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?

Options:

A.

Paper-based drawings are to be used for each option being considered for the building and gardens.

B.

The SAD must include a physically-built miniature model of the Hoy Hall building.

C.

The Architecture Angels' Marketing Director can request a SAD to illustrate the achievability of complex elements of the solution.

D.

The views of the 'Hoy for Hoy Hall' Action Group members are NOT relevant to the business decision made by Architecture Angels' Finance Director when approving the final option.

E.

The SAD should contain high-level costs for all elements of each solution option.

Question 7

There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as

it evolves.

Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2

can be used once, more than once or not at all.

Column 1

1) In order to get an objective

view, the financial transaction

function is to be tested by

someone from Finance who

has had no involvement in its

development.

2) Before the developer works on

the printing function for the

policy documents, the Sales

Manager will review a prototype

of the online application form

for the new coffee shop

insurance product with the

solution tester.

3) Security test scripts have been

provided by the company's

bank. These scripts will be used

to test the link from the

company's website to the

banking system, which is to be

developed specifically to achieve these tests

4.

The addition of the new coffee

shop insurance product may

threaten the stability of the

existing website. As a primary

route to market this is

unacceptable. The website's

capacity to run additional pages

is to be verified before any

other tests are performed.

5.

The Must Have and Should

Have requirements are to be

tested before the Could Have

requirements.

Column 2

    Collaborative Testing

    Repeatable Testing

    Independent Testing

    Prioritised Testing

    Test-Driven Development

Options:

Question 8

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following questions

about Feasibility.

Remember to limit your answers to the number of selections requested in each

question.

Which 2 statements describe the appropriate application of Agile Project

Management when developing the Feasibility Assessment?

Options:

A.

The new Project Manager should NOT be involved in finalising the

Feasibility Assessment.

B.

The Architecture Angels' Finance Director should approve the final

Business Case as part of the Feasibility Assessment.

C.

The Earth Excavations' Head Gardener should contribute to the outline

solutions considered for the gardens.

D.

The different options should be presented to the 'Hoy for Hoy Hall' Action

Group for their feedback before the chosen outline solution is finalised.

E.

The Timber Tigers' Site Manager should be the sole approver of the

finalised Feasibility Assessment before development commences.

Question 9

Each of the following questions includes a list of true statements about individuals from Architecture Angels and Timber Tigers who have been appointed to the

project team. Only 2 statements explain why, in the context of an Agile team, the individual is a suitable candidate for that role.

Remember to limit your answers to the number of selections requested in each question.

Which 2 statements explain why the Architecture Angels' Finance Director would be an appropriate Business Sponsor?

Options:

A.

Is able to delegate most of the required involvement to the Chief Accountant.

B.

Has been friends with the Architecture Angels' Chief Executive since school.

C.

Is the project budget holder.

D.

Is concerned about preventing the costs of refurbishment from escalating and affecting the operations of the company.

E.

Will not distract the Solution Development Team, as is usually too busy to be involved.

Question 10

How should the Project Manager assist the plumbers to deliver the plumbing?

Options:

A.

Split the entire Solution Development Team into smaller teams covering specific locations of the house.

B.

Decide on the location of the radiators on behalf of Architecture Angels.

C.

Establish an inter-team competition to see which team can complete first.

D.

Approve each Timebox before work continues in the next.

Question 11

Using the Project Scenario, answer the following question about the activities in the Agile project lifecycle.

Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Assertion:-

1. The rooms and facilities must be deployed into live use at the end of each Timebox.

BECAUSE

Reason:

Evolutionary Development and Deployment must be combined in a Timebox where the integration of several teams is required.

2. The tasks associated with each Solution Development Timebox should be included

in the Delivery Plan.

BECAUSE

Reason:

A typical Delivery Plan will provide a schedule of Timeboxes and any other high level activities for the imminent Project Increment.

3. The development approach should have been agreed during Foundations.

BECAUSE

Reason:

The Development Approach Definition must be created before Evolutionary

Development can commence.

4. The resources from Timber Tigers and Earth Excavations should have been engaged

before the start of Evolutionary Development.

BECAUSE

Reason:

Commitment to delivery is based on pre-agreed resource levels at the project level.

5. A final Deployment phase should be held after Timebox C has completed.

BECAUSE

Reason:

The Deployed Solution is assessed post-project to confirm whether the expected benefits have been

achieved.

Options:

Question 12

Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox

Plan for Timebox B?

Options:

A.

Marketing Director, in the role of Business Visionary.

B.

Team Leader.

C.

Project Manager and Architect, in the role of Technical Co-ordinator.

D.

Architecture Angels' Senior Management Team.

Question 13

Which 2 statements represent appropriate entries for the Development

Approach Definition?

Options:

A.

The Sales Manager will introduce an awards or bonus scheme, designed

to create competition between the sales assistants.

B.

Once deployed, the number of policies sold through traditional telephone

sales will be compared with the number of sales processed online

through the website.

C.

An easy to use web development tool called 'WebMatrix' is to be used to

develop and maintain the website extension.

D.

The Finance Director has requested a detailed report be produced after

12 weeks, showing costs to date and forecast cost to complete.

E.

Accessibility and performance of the new online quotation area is to be

tested using a tool called Sitebeam.

Question 14

Several of the web developers working on the project have no Agile

experience. When answering the questions in the Project Approach

Questionnaire (PAQ), the Project Manager could not agree with the statement

'all members of the project understand and accept the DSDM approach'.

What action should the Project Manager take?

Options:

A.

Replace the web developers with experienced Agile practitioners.

B.

Agree with the statement in the PAQ and keep a close watch on the web

developers throughout the project.

C.

Organize a training workshop to brief all project-level and Solution

Development Team roles in the Agile approach.

D.

Accept that the web developers are experts in their field and will be

adopting their own approach throughout the project.

Question 15

Xan Insurance Company is a friendly company with no separate private offices

for individual managers. Staff members prefer to wander around the office

space and have one-to-one chats rather than use email or have lots of

meetings.

What action should the Project Manager take when planning for effective

communication throughout the Web project?

Options:

A.

Identify those individuals with power and influence over the project and

what information they require.

B.

No action is required as the existing form of spontaneous informal

communication is suitable for all project level and Solution Development

Team members.

C.

As this is already common practice, assume all Solution Development

Team members have effective communication skills.

D.

Mandate the use of email so that all communications are recorded for

future reference.

Question 16

Answer the following questions about the DSDM Lifecycle.

Decide if each observation is an appropriate application of Agile Project Management for

this project and select the option that supports your decision.

When the project was in the Feasibility phase it was initially proposed by the Finance

Manager that it was a fixed price for a fixed specification' project. The Project Manager

has decided that the best way to tackle it would be to leave the development of the least

valuable features of the product until last.

Is this an appropriate application of the DSDM lifecycle?

Options:

A.

Yes, because the later parts of the project should reflect the least valuable features

of the product being built.

B.

Yes, because in a DSDM project there is no detailed specification upfront.

C.

No, because the Solution Development Team should decide which features are left

until last.

D.

No, because the most valuable features of the project should be delivered last.

Question 17

Xan Insurance Company operates from one location - a large, open-plan

office in the centre of a city. Those employees that will be working within the

Solution Development Team are all based in this office but work at different

ends of the office in separate departments.

What action should the Project Manager suggest to ensure the most effective

collaboration of the Solution Development Team?

Options:

A.

Create an email group for the Solution Development Team to collaborate

on ideas.

B.

Set up a telephone or video conferencing facility so that all members of

the team can collaborate effectively.

C.

Relocate these employees to a new project area, with a number of desks

where the Solution Development Team can sit together.

D.

No action required as these employees are located in the same office.

Question 18

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

Options:

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.

B.

The Project Manager should do nothing during a Timebox.

C.

Attend the Daily Stand-up and discuss any problems at the end.

D.

Update the Team Board with a summary of team progress and the current

status of work.

Question 19

Answer the following questions about the contents of the DSDM

products.

Each of the following questions includes true statements about the project

but only two statements are appropriate entries for the DSDM product

identified.

Remember to limit your answers to the number of selections requested in

each question.

Which 2 statements represent appropriate entries for the Business Case?

Options:

A.

A list of high-level functional and non-functional requirements that the

project should meet written as User Stories.

B.

Coffee shops that sell Fairtrade products and alcohol from local breweries

out perform other coffee shops in the market.

C.

The Sales Manager has been asked to produce a report within the next

two days showing the number of generic insurance policies sold to coffee

shops over the past three years.

D.

The Sales Manager has calculated that the new coffee shop insurance

product will increase revenues by 10% each week.

E.

Market research shows that the number of coffee shop patrons taking

legal action against retailers has increased by 200% over the past two

years.

Question 20

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

Options:

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.

B.

The Project Manager should do nothing during a Timebox.

C.

Attend the Daily Stand-up and discuss any problems at the end.

D.

Update the Team Board with a summary of team progress and the current

status of work.

Question 21

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following question

about assigning the Agile Project Management team roles within this

project.

Lines 1 to 5 in the table below consist of an assertion statement and a

reason statement. For each line identify the appropriate option, from options

A to E. that applies. Each option can be used once, more than once or not

at all.

Options:

Question 22

Which 2 statements represent appropriate entries for the plan for Post-Project

activities?

Options:

A.

The Sales Manager will create a company-wide email showing the

number of policies sold weekly by each of the sales assistants.

B.

Before the product is deployed, the Sales Manager will circulate a copy of

the revised sales procedure for processing coffee shop insurance sales.

C.

The Project Manager will attend Daily Stand-up meetings to observe

progress.

D.

A report showing the number of application forms completed online

through the website for coffee shop insurance policies will be produced

weekly.

E.

Once the new system has been deployed, the time it takes to process

sales online will be compared with the time it takes to process new

policies sold through telephone sales.

Question 23

A difference of opinion on the outcome of an earlier project has created a

'them and us' culture between the Sales Department and the Operations

Department.

What action should the Project Manager take to resolve this?

Options:

A.

Allow the different skillsets to work independently of one another so as

not to create further conflict.

B.

Brief the team and the Business Visionary on the use of an Agile Project

Management approach and the requirement to collaborate.

C.

Appoint only those members of staff who are prepared to work

collaboratively.

D.

Circulate a copy of the Business Case to all members of the Solution

Development Team and project-level roles and invite feedback.