A marketing team is trying to create a new project template for a repeatable workflow. They need to capture phases within each project and ensure tasks support critical-path timelines.
Which two items need to be completed for the efficient use of a project template? (Choose two.)
A project manager needs to share a Custom Form that was created to support their portfolio. What should the project manager understand about this requirement?
Refer to the exhibit.
Tyson has a capacity of 7 hours per day.
What two changes can the system administrator make to this user's workload from within the Workload Balancer to ensure that they are not overallocated? (Choose two.)
Refer to the exhibit.
Which two settings can affect a user's total number of hours shown in the available hours (AVL) column? (Choose two.)
A system administrator is asked to share a financial report with internal users in the system. The system also has external vendors within it who should not see the financial report.
What should the system admin do?
A marketing agency uses Workfront to plan and execute projects for their clients. Each project is associated with a Portfolio to represent the client and a Program to represent the year that the work was completed. A team leader has asked for a list report that shows the actual revenue for each Project and the total actual revenue for each client.
How would a Workfront Developer achieve this?
An engineering team works with an outside vendor who occasionally needs to review and approve documents in Workfront Proof. Which built-in access level would be assigned to the vendor9
Which Workfront objects can date effective billing rates be used with?
A Workfront developer is tasked with building a new custom form to collect project requests. The form will display different sets of options based on different selections, which requires the use of display logic and skip logic in the form.
What are two considerations the developer should take into account when building the conditional logic in the form? (Choose two.)
To which two objects in Workfront can a dashboard be added in the left navigation? (Choose two.)
How can a project manager ensure that progress on the board is also tracked in a project?
The creative services team often completes continuing education courses or specific certifications to expand their skillset. These hours are not linked to a specific project. They have asked the system administrator to create an hour type that will appear on their timesheet.
What are two steps the system administrator would take to create a new hour type named Training and Certifications? (Choose two.)
What are two differences between an issue and a task? (Choose two.)
Which component may be added to Canvas Dashboards, but not legacy Dashboards?
A system administrator is using Dashboards to streamline how teams see and complete their work. What are two best practices to accomplish this in Workfront? (Choose two.)
An admin-level user recommends assigning the role Reviewer & Approver to someone who needs to review a proof. What are two reasons why the admin-level user would make this recommendation9 (Choose two.)
This allows the Reviewer to indicate they have completed their review, even if there is no feedback.
Which reporting element has an option of conditional formatting?
On which types of objects can time be recorded in Workfront?
A project manager is using information in the Portfolio Optimizer to analyze which projects to prioritize. Where is this information coming from?
A team has just created a new project template. Before making the template active, the team needs to ensure that users have access to use the template and the projects created from the template.
Which two items must be configured to achieve this requirement? (Choose two.)
A project manager wants to use Portfolios and Programs to organize projects. What two considerations would apply when using these objects? (Choose two.)