New Year Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

Adobe AD0-E903 Adobe Workfront Project Manager Professional Exam Practice Test

Demo: 21 questions
Total 70 questions

Adobe Workfront Project Manager Professional Questions and Answers

Question 1

A project manager needs to locate the fixed revenue and costs of a project. Where should the project manager look to find this information?

Options:

A.

Business Case

B.

Billing Records

C.

Project Details

Question 2

Given this information regarding a Task:

    Planned Start Date: May 14

    Actual Start Date: May 14

    Planned Completion Date: May 20

    Projected Completion Date: May 22

    Percent Complete: 50%

    Duration: 5 Days

    Planned Hours: 8 Hours

    Status: In ProgressIf today's date were May 19, what would be the Task's progress status?

Options:

A.

Behind

B.

On Time

C.

At Risk

Question 3

A marketing team determines that in the future, their projects must be reviewed by the Project Sponsor before the project is closed. What is the best practice to ensure that each project is properly reviewed and approved?

Options:

A.

Create a new approval process in the global setup area that will ensure that an approval process is attached to all Marketing Projects.

B.

Create a single-use approval process on each project that routes to the Project Sponsor for approval once the project status is set to Complete.

C.

In the project template, add an approval process routing to the Project Sponsor for approval once the project status is set to Complete.

Question 4

When a project owner grants Contribute access on a project to a user with the same access level as the project owner, what can that user do?

Options:

A.

Add a custom form

B.

Attach a template to the project

C.

Add tasks

Question 5

What parent object can have child objects?

Options:

A.

Issue

B.

Project

C.

Portfolio

Question 6

Which wildcard should be used on a project report when filtering for projects that have a planned completion date greater than 1 month from the current date?

Options:

A.

TODAY + 1bm

B.

TODAY + 1m

C.

CURRENTDATE + 4w

Question 7

Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday.

Why may this be the case?

Options:

A.

The primary task owner has time off logged in Workfront.

B.

The team needs to review the task before confirming the start date.

C.

The task duration and planned hours are set to begin on Friday.

Question 8

Which project elements can be used to measure a project’s adherence to its original schedule?

Options:

A.

Number of tasks, actual completion dates, and project status

B.

Project baselines, planned completion dates, and actual completion dates

C.

Workload balancer data, planned completion dates, and expenses

Question 9

Which field is used to create a milestone step on a milestone path in the Setup area?

Options:

A.

Status

B.

Description

C.

Key

Question 10

A video designer is spending an excessive number of hours on a project that involves editing a TV commercial. The tasks are keeping the designer from completing other assigned work. After discussing the matter with the designer, the project manager determines that the additional hours for this project are necessary and suspects that the number of hours budgeted for the video designer's time on this project was too low in comparison to the actual need. The project manager will need data to illustrate the problem and potentially request more resources for this project so that the designer can still meet commitments on other assigned work.

Which native Project tool is designed to illustrate data on how the Planned Hours for the video designer on this project vary from the Actual Hours spent on the project?

Options:

A.

Utilization

B.

Workload Balancer

C.

Hours

Question 11

The executive team at Company A has asked the Workfront System Administrator how they can get visibility into the health, importance, and strategic alignment of active projects across the organization so that they can quickly make data-driven business decisions.

Which report grants the executive team this visibility?

Options:

A.

A project report showing active projects grouped by portfolio showing project condition, project priority, and custom data aligning the project initiative to business goals.

B.

A portfolio report showing all projects grouped by team showing project condition, the alignment score, and custom data aligning the project initiative to business goals.

C.

A program report showing active projects grouped by department showing program health, project urgency, and custom data aligning the project initiative to business goals.

Question 12

A project manager has been asked to work on a cross-departmental company-wide initiative. There will be many individuals assigned to each task.

What should the project manager ask users to do when it comes to completing tasks?

Options:

A.

Users do not need to complete tasks when multiple users are assigned.

B.

Mark the task as "Done with my part."

C.

Make an update and tag the project manager.

Question 13

A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?

Options:

A.

Actual Completion Date

B.

Progress Status

C.

Status

Question 14

Executive stakeholders require both current metric reports and a weekly recap on a project.

How can both needs be met?

Options:

A.

Create a program-specific dashboard for the metrics and set up a weekly automated report to send.

B.

Create a program-specific dashboard for the metrics, then download a dashboard weekly to email to the stakeholder team.

C.

Create a program-specific dashboard for the metrics and add a calendar reminder for the team to review the report.

Question 15

A portfolio owner has asked to see milestone statuses for all projects in their portfolio. The report must filter out any complete projects. What steps should the project manager take to create this view?

Options:

A.

Visit the Dashboards page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects.

B.

Visit the Projects page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select "Show the Milestone view on the Details tab."

C.

Visit the Reports page and create a Project report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select "Show the Milestone view on the Details tab."

Question 16

Which project status defaults the project condition to On Target?

Options:

A.

In Progress

B.

Idea

C.

New

Question 17

A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.

Which date type would the project manager utilize?

Options:

A.

Estimated Date

B.

Projected Date

C.

Planned Date

Question 18

How is the primary assignee of a task determined?

Options:

A.

By the user on a task that has a primary job role.

B.

By the Home Team assigned to a task.

C.

By the user that is assigned first to a task.

Question 19

A project manager has been asked to create a report showing the planned completion date for all the project manager's projects. The report must show results in a calendar view and all entries should be purple. What steps should the project manager take to create this view?

Options:

A.

Visit the Reports page and create a new report. In the filter, update the project Owner ID field with the project manager’s name and set the Color ID field to purple. Add a column for Planned Completion Date and set the default view to “Calendar View.”

B.

Visit the Calendars page and create a new calendar. In the filter, update the date field to Planned Dates and update the Project Owner ID field with the project manager’s name. Set the color to purple.

C.

Visit the Reports page and create a new calendar. In the filter, update the Project Owner ID field with the project manager’s name and set the Color ID field to purple. Add a column for Planned Completion Date.

Question 20

A system administrator has created a Marketing Request Queue that routes to the marketing team. This team needs to manage various incoming requests from the organization through emails, instant messaging, and conversations. Team members receive request notifications in their emails but are still having difficulties monitoring and prioritizing incoming requests.

Which reports would be helpful to have on a dashboard for the marketing team to manage incoming work requests?

Options:

A.

Four reports showing the entry date of each request, i.e., one that shows requests in a New status, one that shows requests in an In Progress status, a third report that shows recently completed requests, and a fourth report that shows the schedule assigned to each team member.

B.

Two reports showing the priority and actual completion date of each request, i.e., one that shows active requests and another that shows recently completed requests.

C.

Three reports showing the priority and entry date of each request, i.e., one that shows requests in a New status, one that shows requests in an In Progress status, and one that shows recently completed requests.

Question 21

A portfolio manager has inadvertently given too much access to all the projects in their portfolio to Program Manager A.

How does the portfolio manager rectify the situation to ensure that Program Manager A has Manage access only on their own program?

Options:

A.

Share the program with Program Manager A with Manage access and ensure the system administrator adjusts Program Manager A's access level.

B.

Share the program with Program Manager A with Manage access and ensure Program Manager A understands they cannot manage the rest of the portfolio.

C.

Share the program with Program Manager A with Manage access and remove Program Manager A's Manage access on the portfolio.

Demo: 21 questions
Total 70 questions